Underwriting Corruption
Britain's Role in Promoting Corruption, Cronyism and Graft

by The Corner House

first published 10 December 2000

Summary

This Corner House submission to British House of Commons' International Development Committee's Inquiry into corruption urges the Committee to examine the structural causes of corruption in the countries of the South, such as the policies and programmes that Western governments and agencies push on these countries. It recommends that the Committee focus less on the perceived "lack of political will" to tackle corruption and more on those vested interests that generate immense political will to block investigations when they are initiated and to undermine anti-corruption drives.

Contents

Summary and recomendations

1. Corruption - broadly defined as "the abuse of public or private office for personal gain"1 - has become a major international concern. Its impacts on development, democratic accountability and Third World debt are profound, with the burden falling most heavily on poorer sections of society (paras 9-19).

2. Surveys reveal widespread acceptance of bribery among European companies operating in the developing world. Anti-corruption drives by popular movements and governments in the South have exposed many instances of alleged corruption involving UK companies, some of which are now before the courts.

3. In many cases, these corruption allegations relate to companies or projects which have received tax-payer support through UK-backed agencies such as the World Bank (paras 20-56), the UK Export Credits Guarantees Department (ECGD) (paras 57-84) and the Department for International Development (DfID). While making no judgement on individual cases, The Corner House believes that the overall evidence of public monies being mismanaged or abused is sufficiently solid to merit investigation by the UK National Audit Office.

4. The Corner House also believes that there is an urgent need to shift the focus of anti-corruption measures. In seeking to "explain" corruption, most commentators tend to dwell on developing countries, not industrialised ones - on the bribe-takers, not the bribe givers. The intimate connection between corruption in the South and the institutional culture, bureaucratic practices and priorities of public and private institutions in the North is thus effectively obscured.

5. Indeed, if corruption is growing throughout the world, it is in large part fueled by policies and programmes that are being pushed by Western governments and which are further underwritten by poor governance and misdirected funds in the North.

6. The Corner House urges the Committee to direct its investigation towards examining these structural causes of corruption. Adopting this approach, it believes, may encourage policy makers:

  • To focus less on the perceived "lack of political will" to tackle corruption and more on those vested interests that daily generate immense political will to block investigations when they are initiated and to undermine anti-corruption drives;
  • To look not only at how regulations could be improved but also at the daily institutional practices that actively encourage the flouting of existing development guidelines and anti-corruption regulations; and
  • To look not only at ways of opening up decision-making to public participation and scrutiny but also at the institutionalized racism that assumes the Third World to be inherently corrupt and corruptible and which thereby underwrites bribery even where nominally accountable procedures are in place.

7. More specifically, The Corner House would urge the Committee to examine the links between the growth of corruption and UK public and private sector practices. In particular, it would draw the Committee's attention to:

  • The continuing failure of UK-backed Multilateral Development Banks to address an institutional culture that rewards the approval of loans over the rigorous scrutiny of their impacts, including governance impacts (paras 50-55);
  • The failure of UK agencies such as the Export Credits Guarantee Department (ECGD) to introduce the binding sanctions and rigorous investigative procedures necessary to deter and punish corruption, for example through the blacklisting of companies involved in corrupt practices (paras 62-81);
  • Deficiencies in UK company law and private sector corporate governance that encourage corruption, for example, by failing to require the disclosure of information on corruption allegations to shareholders (paras 92-98);
  • The reluctance of the UK regulatory authorities to investigate allegations of corruption and the failure of the UK government to bring prosecutions on the basis of existing anti-corruption legislation (paras 77-81 and 100-102);
  • The imposition by the World Bank, the International Monetary Fund and bilateral aid agencies of rapid privatisation programmes which, in the absence of an appropriate legal and institutional framework, have encouraged a "fire sale" approach to the sale of public enterprises which has in turn provided fertile ground for cronyism and corruption (paras 103-106).

Economic impacts of corruption

9. Corruption is now a routine feature of many development projects and programmes. Every year, Western businesses pay huge amounts of money in bribes to win friends, influence and contracts. These bribes are conservatively estimated to run to US$80 billion a year - roughly the amount that the UN believes is needed to eradicate global poverty.2 Those paying the bribes include multinational and national companies, consultancy firms and even government agencies - national export credit agencies coming in for particular criticism.3

10. Corruption carries heavy economic and social costs; it undermines development and distorting democratic processes and rational decision-making.

11. The amount of money lost to corruption that could, and should, be directed towards public services and to the development of democratic institutions is significant. Although the Committee's inquiry is focused on corruption in the field of international development, it is important to scotch the racist assumption that corruption is a problem that is primarily restricted to the South. Fraud, embezzlement and bribery are equally pervasive in the North - and their economic impacts are no less detrimental. In the United States alone, fraud and corruption claim $400 billion per year.4 A recent report published by the Association of Certified Fraud Examiners found that organisations - public and private - were losing 6 per cent of annual revenue to fraud and corruption.5

12. The direct economic impacts of corruption are substantial.6 According to the Asian Development Bank (ADB), "corruption can add between 20 per cent and 100 per cent to the procurement of government goods and services", with overall corruption-related losses totaling, in some cases, "more than a country's foreign debt".7 Transparency International estimates that, on average, five per cent of national budgets go astray.8 A leaked 1998 World Bank report estimates that 20 per cent of World Bank loans to Indonesia were embezzled by corrupt officials under the Suharto regime (see Appendix 2). Some analysts have alleged the Bank was not only aware of the corruption but did little to prevent it.9

13. Corruption also negatively affects the selection of development projects, as well as their quality, financial viability and distributional outcome. As the ADB notes, corruption:

  • Diverts "resources away from social sectors and toward defense and major infrastructure projects";1011
  • Reduces the life of assets, "as resources are directed away from maintenance and toward new projects and equipment";12 and
  • Encourages "the design or selection of uneconomical projects because of opportunities for financial kickbacks and political patronage.13

It's the poor that pay the price

14. The ADB warns that the "costs of corruption are often borne disproportionately by the poor, while the provision of public goods and services is skewed towards the rich, the powerful and the politically well connected."14 UK Parliamentarian Hugh Bayley is more blunt: "Bribery is a direct transfer of money from the poor to the rich."15 Corruption makes the poor poorer - not only do they end up paying more for services but they also lose out when money that could have been spent on projects that would directly benefit their communities is diverted to big expensive projects with lucrative commissions. Hard-won public health and environmental legislation may also be undermined through "illicit payments to prevent the application of rules and regulations in a fair and consistent manner, particularly in areas concerning public safety, law enforcement or revenue collection."16

15. In many cases, corrupt contracts lead to uneconomic projects and increased public debt. Again, it is the poor who pay the price - through cuts in public expenditure, poorer services and higher prices for basic needs. The case for reviewing Britain's debt portfolio and writing off debts incurred through corruption is overwhelming.

16. Ironically, but predictably, efforts to curb corruption through procedures that are designed to meet the bureaucratic requirements of funders, rather than local realities, frequently result in procedures that can also work to the detriment of poverty alleviation and sustainable development. As a World Bank Consultant notes of the World Bank's Third Fisheries Project in Bangladesh, which was intended to increase the production and availability of affordable fish for poorer people:

"The [project] was excellently designed but nearly ruined by the World Bank's rules ... Fish fingerlings cost Taka 60 per kilo and were expected to fall to Taka 45 as a result of the project's work. Instead the price rose to nearly Taka 120. What had happened was that the World Bank had imposed some standard rules of its own. Fingerlings had to be bought under International Competitive Bidding, so documents had to be in English.

"The numbers of bidders had to be limited to 9. Bidders had to prequalify each year, having to buy the 45 page prequalification documents in English. Having prequalified, they had to answer an advertisement to buy the bidding documents, and then had to prepare the actual bids. The whole process took about 5 months. However, the sort of people who dealt in fish and fish fingerlings were invariably in a small way of business, and were only literate in Bengali. They had neither the language to deal with the World Bank's documents, nor the cash flow to handle the hundreds of tonnes of fingerlings that such contracts demanded. This process was followed each year. To deal with such contracts, "musclemen" or "mastans" entered the scene. They went about armed and fixed the price. They brought the project to the brink of disaster. The consultants employed to manage the contract pointed out the faults in this system many times to the Bank's staff, but the Bank was insistent: The rules must be followed."17

Development failure - for whom?

17. What constitutes a development failure from the point of view of the poor and civil society, however, may well constitute a development success from the point of view of funding agencies, consultants and companies involved in a project. Even ill-conceived anti-corruption programmes, for example, are evidence of some sort of "action" for which institutions can - and do - claim credit. Likewise, by lubricating deals, corruption may enhance the career prospects of aid bureaucrats or company employees whose promotion often depends on the rapid disbursement of loans, the sealing of deals or the implementation of projects.

18. Addressing these institutional "benefits" of corruption is as critical as documenting and analyzing its financial and social costs. It is, after all, the "benefits" of corruption that fuel its growth and sustain its practice. Unless action is taking within institutions - from multilateral development banks to bilateral agencies and the private sector - to ensure that the institutional costs of indulging in corruption - or turning a blind to it - outweigh the benefits, there is little prospect for change.

19. Unfortunately, as the next sections show, the UK's record in this regard is poor.

Corporate governance failures, corruption and UK-backed International Finance Institutions: The World Bank

20. A significant percentage of the UK's current aid budget is directed through Multilateral Development Banks (MDBs), including the World Bank group.18 Britain sits on the Board of the World Bank and, as such, has direct oversight of its use (and misuse) of UK tax-payers' money.19 As a Board member, however, Britain has conspicuously failed to insist on the high standards of financial management that UK taxpayers have a right to expect.

21. Although the World Bank has recently initiated anti-corruption measures - creating new oversight structures and increasing staff with expertise in financial management - major shortcomings are evident in their implementation. In addition, the Bank's Executive Board has conspicuously failed to address well-documented (and acknowledged) institutional practices within the Bank that encourage corruption. Disturbingly, the UK has supported many projects despite evidence of corruption, or their failure to comply with the Bank's own anti-corruption measures.

Ignoring Corruption: Russia and Indonesia

22. Internal World Bank documents and external reports by the US Government and others now provide plentiful evidence that the World Bank's Board, which is responsible for ensuring that loans are spent as intended, has approved loans to countries with a known record of corruption, despite such countries failing to comply with the Bank's own anti-corruption regulations and despite warnings that the loans were likely to be misspent. The cost to the UK taxpayer of such mismanagement runs into millions of pounds.

23. In the Summer of 1997, for example, Business Week alleged that at least $100 million from a $500 million Russian coal sector loan was either misspent or could not even be accounted for.20 A little over a year later, the Financial Times estimated the amount stolen in the coal sector loan to be much higher, as much as $250 million.21

24. In Indonesia, according to a 1997 internal World Bank study known as the Dice memorandum,22 some 20 to 30 per cent of all development funds, totaling several billion dollars, have been systematically diverted through corruption (see Appendix 2). These figures accord closely with estimates by other experts, such as former Indonesian Finance Minister Sumitro Djodjohadikusomo and Jeffrey Winters of Northwestern University. Winters alleged in July 1997 that shoddy accounting practices by the World Bank had allowed the misappropriation of as much as $8 billion dollars of World Bank lending to Indonesia over the past 30 years.23 In effect, successive UK World Bank Executive Directors, who are duty bound to ensure that UK money disbursed through the Bank is properly spent, appear to have permitted the misuse of some $405 million of UK taxpayers' money.24 And this in Indonesia alone. The case for a National Audit Office investigation into the Bank's lending programme in Indonesia would thus seem to be overwhelming.

25. As with the Russia loans, however, the Bank continued to pour money into Indonesia, despite the findings of the Dice report. In the 15 months after the report was written, the Bank committed and disbursed over $1.3 billion more to Indonesia without any effective measures to address the problems identified by Dice. In October 1998, with plans to commit and disburse two billion dollars more over the next nine months, a second Bank mission, headed by Jane Loos, recorded the following:

"Our mission confirms earlier reports on corruption in Indonesia: that it is pervasive, institutionalised and a significant deterrent to overall growth of the economy and effectiveness of the Bank's assistance ... Despite apparent compliance with World Bank guidelines and documentation requirements for procurement, disbursement, supervision and audits, there is significant leakage from Bank funds ... Bank procedures/standards are not being applied uniformly ... The [World Bank] auditing requirements have been allowed to deteriorate into a superficial exercise; even an agency with overdue audits was not excluded from receiving new loans"25

Corruption and Dams

26. Nor are the Russian and Indonesian examples one off aberrations. Research undertaken by The Corner House on dam projects funded by the World Bank has revealed widespread corruption within the sector. Recent examples of World Bank-funded dam involving corruption - documented in Appendix One - include the Lesotho Water Highlands Project, and the Itaipu and Yacyreta projects on the Parana River in Brazil, Paraguay and Argentina. Yacyreta, funded to the tune of $860 million by the World Bank, has been described by Argentinean President Carlos Menem as "a monument to corruption". The dam's costs soared from an original estimate of $2.7 billion to 11.5 billion, and the still unfinished dam is currently 10 years behind schedule.26 Itaipu was originally projected to cost some $3.4 billion, but skimoffs by the then military rulers of Paraguay and Brazil and their cronies contributed to the cost skyrocketing to around $20 billion.27

27. Other studies indicate similar levels of corruption in other sectors.28 Bank staff themselves admit that the Bank has for years been reluctant to address corruption risks openly and directly with borrowers but argue that the Bank is now taking the issue seriously.29 Nonetheless, a full five years after the Bank first adopted "internationally accepted standards of effective management control",30 and four years after the Bank's President committed the Bank "to fight the cancer of corruption",31 its own rules continue to be flouted - with the apparent complicity of the Bank's own Executive Directors.

Flouting the Rules: The GAO's View

28. As the US General Accounting Office (GAO) reported in a major study of the Bank's fiscal management control, published in April 2000, the Board continues to approve many projects which fail to meet the Bank's minimal financial management requirements.32 Of 12 projects in "corruption-prone" countries randomly selected by the GAO, "six ... did not meet the Bank's minimal financial management requirements at the time that the Board approved the projects".33 The report continues:

"Our review of 12 randomly selected projects approved by the Bank since November 1998 identified 5 projects in which the borrowers' implementing agencies had little or no experience managing development projects, according to Bank records and staff ... Furthermore, for 3 of the 12 projects, the Bank determined that the borrowers' implementing agencies had particularly weak capacity for carrying out procurement in accordance with Bank rules ... For four projects, the implementing agencies were not yet functioning and did not have key staff or operating procedures in place."34

As a result of these and other deficiencies:

"The Board may not have had sufficient information to assess the borrower's capacity when approving these loans."35

Disturbingly, in six of eight projects where Bank staff "had flagged weak management capacity, corruption, or political interference as a critical risk", the project appraisal documents "did not describe what specific supervisory actions the Bank planned to take to mitigate the risks."36 It is not known whether or not the Board requested such measures when it approved the projects.

29. The GAO also notes that the Bank's new anti-corruption procedures only apply to "about 208, or 14 per cent, of the Bank's 1500 projects" and that "Bank studies indicate that management weaknesses persist in ongoing projects."37 Recent procurement audits, for example, "show a lack of understanding of and noncompliance with Bank procurement rules among many (17 of 25) borrowers subject to these audits."38

30. Although the GAO review notes that the Bank has made "significant progress" in introducing anti-corruption measures, it concludes, "further action will be required before the Bank can provide reasonable assurances that project funds are spent according to the Bank's guidelines."39 Given the huge sums that have been disbursed since the Bank began operating over 50 years ago - some $170 billion40 - this criticism, which is echoed by a succession of internal Bank reports dating back to the early 1990s, is profoundly disturbing.41

31. Among the many problems identified by the GAO, the following are particularly pertinent to the Committee's inquiry:

  • "Many borrowers still have weak structures and limited managerial capacity, according to Bank records and officials."42 The Bank itself "identified deficiencies in financial accounting, reporting and auditing in many projects";43
  • The Bank's own internal oversight mechanisms are "weak, according to several officials we spoke to";44
  • The Bank lacks "a central focal point for reporting and reviewing allegations of wrongdoing and sufficient expertise to investigate allegations of wrong doing";45
  • Many instances of corruption are not reported to the Bank's Oversight Committee on Fraud and Corruption. "During our June 1999 visit to one country where the Bank identified corruption to be a serious issue, we found that over 30 allegations of wrongdoing that were reported locally to Bank officials had not been reported to the Committee";46
  • The Bank's Investigations Unit lacks does not have "the necessary stature and independence";47
  • The Bank has failed to carry out more than rudimentary assessments of the procurement and financial management systems of its ten top borrowers, which collectively received 62 per cent of the Bank financing in 1999;48
  • "We found little evidence that improved financial management supervision has resulted in any increase in the quality of project auditing ... According to Bank managers we spoke to, supervision of project audits is not considered the responsibility of bank staff, and Bank staff conduct little quality control of audit work;"49 and
  • "Bank monitoring efforts do not fully assess the impact of Bank efforts to improve the strength of its management control over project lending. In particular, the Bank's monitoring efforts do not focus on key deficiencies in management controls highlighted by Bank studies in the past few years. Consequently we were unable to determine the extent to which the Bank has corrected these deficiencies."50
  • 32. Other studies reveal that auditing of World Bank projects often amount to looking at the books, without checking whether the records match reality.51 Between 1997 and 1999, only 50 projects out of a total of 250 were audited. Yet 100 contracts (out of a total of around 45,000) were declared "misprocured". Their total value was over $45 million. Audits are "generally innocuous, untimely and therefore useless" and provide only "cosmetic accountability."52

33. Conflicts of interest are also pervasive in World Bank auditing. The "independent firms of international repute" which the Bank hires to carry audits are the same ones it employs to set up the accounts, information systems and financial management of its projects.

34. The probity of some of the auditing firms used by the Bank also leaves much to be desired. Societe Generale de Surveillance (SGS) of Switzerland, the company appointed by the Bank to investigate corruption in Bank projects, has itself admitted to paying "a substantial commission" in 1992 to obtain a government contract for inspection services in Pakistan.53 Furthermore, according to the US Security and Exchange Committee, PriceWaterhouse Coopers, the auditor hired in 1998 to help the internal Fraud and Corruption Unit of the Bank, was found guilty of "not only a lack of sufficient global safeguards, but also a systematic failure by professionals ... to adhere to even their own firm's existing controls."54

35. The GAO study concludes that the Bank's recently introduced anti-corruption measures, although improving, "are not yet strong enough to provide reasonable assurances that project funds are spent according to the Bank's guidelines."

36. The Bank has criticised the GAO report for its narrow focus on internal financial management of loans. As a result, the Bank argues, the GAO has missed "the broad dimensions of [the Bank's] overall governance and anti-corruption work", in particular through its lending for adjustment and public sector reform. Such lending, the Bank states, arguably constitutes "the most important dimensions of the Bank's anticorruption work." In reality, however, the Bank's structural adjustment and public sector reform programmes have exacerbated corruption for reasons that are explained in paras 103 to 106 below.

37. Given the millions of pounds of UK taxpayers' money spent every year by the Bank, The Corner House urges the Committee to press the UK Government to follow the US lead and institute a National Audit Office investigation of the Bank's fiscal management regime, including the circumstances surrounding the disbursement of loans that have been identified as problematic.

38. Such an inquiry should look not only at the flouting of procurement and auditing rules by World Bank staff but also at the rules themselves. As Tim Tucker, a consultant who has worked for the World Bank, has pointed out, existing rules can easily be exploited by those who know the ropes for corrupt ends.55 Moreover, the ritualistic application of rules, regardless of context, can, as in the Bangladesh fisheries project example cited above, result in outcomes which are the opposite of those they are intended to achieve. Likewise efforts to increase transparency that rely on form filling, though useful in providing a paper trail that can help investigation, may ultimately serve only to bury wrongdoing under reams of paper. Tucker's experiences would suggest that new procedures alone will not address the problems revealed by the GAO and other bodies. Corruption and the financial mismanagement that facilitates it is most likely to be curbed through increasing the likelihood of detection, not least through more proactive investigation of those involved in making bids, in addition to staff incentives that reward greater oversight.

39. The Corner House further recommends that any investigation should not be restricted to considering the Bank's internal controls over investment lending: it should also examine the Bank's apparent inability to address well-identified institutional practices and procedures that allow corruption to flourish. These are discussed in more detail below.

Evading Responsibilities - Kazakhstan, Lesotho and Pakistan

40. Although the Bank has debarred a number of companies from bidding for contracts after they were found guilty of corruption, such companies have tended to be smaller consultancies or sub-contractors (the majority of them British - 36 out of 54 listed in June 2000).

41. The Bank, however, has shied away from taking action against larger firms - even to the point of allegedly suppressing information. Tim Tucker recalls the Bank's reaction to his discovery of evidence suggesting that one of the world's largest accountancy companies had submitted false information as part of its bid to win a World Bank contract in Kazakhstan. As he recalls:

"When I showed [the evidence] to World Bank's Task Manager, I was told that I had not shown him [the] document to him, because if I did so show it to him, the World Bank would have to stop [the company] bidding for a 3 year minimum."56

42. Leaked correspondence between the Bank and the Government of Lesotho over the Lesotho Highlands Water Project also provide an insight into the Bank's priorities when faced with evidence of financial mismanagement and corruption. Nine companies and three international consortia involved in the project are currently on trial in Lesotho, charged with bribing Masupha Sole, the project's former director, in order to win construction contracts. The correspondence suggests that the Bank knew as early as 1994 that an audit of the project's accounts had revealed serious mismanagement.57 The Bank's reaction, however, was to berate the Lesotho authorities for having suspended Masupha Sole from his post pending an investigation. Their reason: it would interfere with project construction timetables and could lead to costly overruns.58

43. It also emerges that the Lesotho government was already investigating the corruption allegations against Sole at the time that the Bank approved new loans in June 1998 for the second phase of the project - constructing the Mohale Dam.59 The Bank pushed for Mohale to be built immediately, rather than in a decade's time when its water would be needed in South Africa, because the contractors were in place and it would therefore be cheaper to build immediately than waiting.60 Many of these contractors are now alleged to have paid bribes to obtain their contracts.

44. Although the Bank has now instigated an internal investigation into the corruption charges, the investigators - Arnold and Porter, a prestigious Washington-based law firm - have reportedly been subject to restrictions. For example, on the basis of meetings with Bank officials, Non-Governmental Organisations have alleged that the firm has been denied complete access to World Bank files and is also only allowed to copy files which it could have obtained via third parties.61 This is denied by the Bank.62 Once completed, the investigation will not be made public.

45. Meanwhile, NGO demands that any conviction in the Lesotho courts should result in the convicted companies being debarred from World Bank contracts have been rejected by the Bank. Convictions in the court, the Bank has stated, will have no bearing on the Bank's future dealings with any of the companies. Instead, the Bank is insistent that it will only debar companies if its own internal investigations show that a company has been involved in corruption involving a project component specifically financed by the Bank. Since the Bank only made a small contribution to the multimillion dollar scheme, this would mean that few - if any - companies are affected. Although the World Bank's President, James Wolfensohn, recently committed to wait for the findings of the national trial in Lesotho, it is still unclear whether the World Bank will refer to its internal investigation or the national trial in Lesotho as concerns the possibility of applying sanctions on companies found guilty of corruption.63

46. In any case, the Bank's position is based on the narrowest legal interpretation of the Bank's guidelines and a singularly selective view of the Bank's involvement in the project. Not only did the Bank finance the design of the project; it was also responsible for setting up and coordinating the financing programme.64

47. In Lesotho, the World Bank, having initially discouraged investigation into the corruption charges, is now helping to fund the prosecution of suspected companies. By contrast, in Pakistan, the World Bank's partner organisation, the International Monetary Fund, has actively intervened to crush corruption prosecutions. In 1998, some 21 Western companies were investigated by the national corruption agency for alleged kickbacks to the government of Benazir Bhutto and for over-pricing.65 Although all the companies filed sworn statements denying corruption, six of them subsequently confessed to offering bribes.66 So serious were the allegations that the World Bank sent in a special team of investigators.67 Yet far from receiving support from Western governments for its anti-corruption efforts, Pakistan was warned by the British, US, Japanese and Canadian governments that its clash with the companies would put off other investors.68 The IMF went so far as to make a package of loans at the end of 1998 conditional on the government dropping the charges against the companies.69

Unscrutinised Consultancies

48. Although tenders for major constructing projects are subject to competitive bidding, consultancy contracts - which absorb ten per cent of the Bank's annual lending - are not. Such contracts are particularly prone to corruption, since companies derive obvious advantages from the Bank hiring consultants whose recommendations are likely to lead to contracts. As Transparency International notes: "Consultants have a particularly powerful function in the early stages of a project ... If the consultants are associated in some way with a contractor who has successfully built thin arch dams, it should not surprise anybody if the consultant comes up with the proposal to build a thin arch dam, even though the topographic and rock conditions might favour a rock fill dam."70 TI recommends that consultants should be required to disclose any factors that would reduce the consultant's independence.71

Corporate Lobbying and Cronyism

49. Forty-five per cent of the $25 billion that the World Bank lends each year is disbursed directly to foreign companies through International Competitive Bidding. The majority of these contracts go to companies from the G7 countries. A host of specialised lobbying firms have grown up to help companies win these deals, many started by former World Bank staff and representatives. These lobbyists keep an ear out for forthcoming projects, arrange meetings between their clients and Bank staff, and help their clients structure bids. Sometimes they or their clients lobby the Bank to take on particular projects. Such practices are not conducive to transparency: instead they encourage patronage networks and cronyism.

The Pressure to Lend

50. Several factors make it difficult for the Bank to ensure that its funds are properly used. Of these, the most consistently well-documented in internal Bank reports are the deep-seated institutional pressures on the staff to "deliver" projects. As a 1992 report by the Bank's Portfolio Management Task Force, led by Willi Wapenhans, makes clear, the Bank's "pervasive preoccupation with new lending" takes precedence over other considerations.72 According to the Task Force, "a number of current practices - with respect to career development, feedback to staff and signals from managers - militate against increased attention to project performance management." In the subculture which prevails at the Bank, Wapenhans said, staff appraisals of projects tend to be perceived "as marketing devices for securing loan approval (and achieving personal recognition)"; no one bothers to take government's implementation capacity into account when calculating economic rates of return; "poor policy environments", institutional constraints", lack of "sustained local commitment" - all of these are often simply ignored in the rush to push projects through and keep them going.

51. The Bank's institutional priorities and management structures have thus encouraged staff to flout internal policy directives and borrower governments to ignore loan conditions. Unsurprisingly, the "credibility of [loan agreements] as binding documents has suffered" and "evidence of gross non-compliance [with Bank legal covenants] is overwhelming." When borrowers disregard loan conditions, the typical response of Bank management has been to look the other way or waive the relevant requirements, unless public pressure forces them to do otherwise.

52. Since 1992, the Bank has introduced a number of initiatives intended to address the problems identified by Wapenhans. However, far from remedying the problems, they have in many respects made them worse, not least by streamlining business procedures in order to speed up loan approvals and by introducing new rewards for staff, who move projects through the approval process at a faster place, rather than for those who comply with policy.73 Indeed, a succession of internal reports has continued to criticise the culture of loan approval - where staff are rewarded above all for pushing money - as a major cause of project failure and "leakage" (the Bank's euphemism for graft).7475 In at least one instance, the full findings of one critical report - a 1997 review of the Bank's project portfolio by the Quality Assurance Group - were never officially shared with Board members. Significantly, the report concluded:

"The lessons from past experience are well known, yet they are generally ignored in the design of new operations. This synthesis concludes that institutional amnesia is the corollary of institutional optimism."76

Clientitis

53. Like the "pressure to lend", the Bank's desire to keep lending to its client governments - "clientitis", in the words of Bruce Rich, International Program Director at Environmental Defense, a US non-governmental organisation - has long been identified as a major cause of poor loans being approved by the Bank. Yet, again, however, it is a problem that the Bank's management and Board has singularly failed to address, exacerbating the problem of corruption and poor project quality. Even when Bank staff have been well aware of corruption in loans, they have frequently ignored it in order to maintain the flow of lending.

54. In a February 1999 study of lending to Indonesia, the Bank's own Operations Evaluations Department (OED) notes: "Warning signals were either ignored or played down by senior managers in their effort to maintain the country relationship. Some staff feared the potential negative impact on their opportunities that might result from challenging mainstream regional thinking."77 Significantly, the Bank's reluctance to fall out with a major borrower led it to downplay major problems which internal reports had revealed in the Indonesian banking system, with the result that the "Bank's readiness to address the subsequent financial crisis in Indonesia was seriously impaired."78

Penalising Integrity

55. World Bank staff are frequently reluctant to raise questions that might slow down a loan because they fear that doing so will adversely affect their career. Internal Bank memoranda and reports have identified this as a major problem in addressing the Bank's "culture of loan approval" and, indeed, corruption. In its 1999 report on Indonesia, for example, the OED notes that staff who had drawn attention to major problems in the Indonesian banking sector were perceived to have suffered "unjustified penalties to their career prospects."79

Some Questions

56. The UK government has a direct responsibility for the failure of the Bank to carry out the necessary reforms that would reduce corruption in the Bank's own projects. The Committee may wish to inquire of government ministers:

  • How much UK taxpayers' money has been lost as a result of corruption in World Bank and IMF loans?
  • How the UK Executive Director and the Treasury justify the continuing approval of loans that do not meet the World Bank's own fiscal management standards?
  • What measures the UK government intends to take to address the well-identified institutional failures within the Bank that encourage the mismanagement and misuse of loans?
  • When was the UK Executive Director of the World Bank first made aware of corruption allegations in the Lesotho Highlands Water Project? What action was taken?
  • What instructions were given by the UK government to the UK Executive Director at the IMF in the matter of company corruption in Pakistan?
  • What was the outcome of the World Bank's investigation into corruption in Pakistan? Will any of the companies which have admitted corruption be debarred from bidding for future World Bank contracts? If not, why not?

Corruption, corporate governance and the UK Export Credits Guarantees Department

57. Within multilateral institutions such as the World Bank, the UK's scope for pressing for action to address the corporate governance failures that nurture and encourage corruption is limited by the need to agree changes with other governments. In the case of UK public institutions, this constraint does not apply to the same degree.

58. The UK's record on addressing pertinent institutional failures within UK government agencies that support development projects in the South is thus a test of its commitment to combating corruption and promoting better governance.

59. The Corner House has not examined in depth the measures taken in this regard by the Commonwealth Development Corporation or the Department of International Development (previously the Overseas Development Administration), although it notes that corruption allegations have surrounded a number of DfID/ODA programmes. Most recently, the Comptroller and Auditor General of India has reported major mismanagement of funds by the Karnataka Forests Department in the DfID-backed Western Ghats Forestry Project in India - described by the previous Conservative administration as "Britain's flagship aid project".80 The Comptroller General's report is appended (see Appendix 1).

60. The Corner House has, however, examined evidence of alleged corruption in a number of projects backed by the UK Export Credits Guarantee Department (ECGD).

61. This evidence strongly suggests that the agency, which underwrites the export contracts and investments of UK companies working abroad, has inadequate procedures to pursue or guard against corruption with the vigour and application that the UK public has a right to expect. New measures introduced to combat corruption, though welcome, also fall far short of credible responses to the institutional failures that are evident in the agency's management and operations.

Inadequate Due Diligence Procedures

62. A focus of recent concern over the ECGD's procedures for combating corruption has been the Lesotho Highland Water Project, where 3 ECGD-backed UK firms are currently being prosecuted for allegedly bribing a top official in order to gain project contracts.81 The three companies charged are: Balfour Beatty, Keir International and Sterling International. The ECGD's support for the project amounted to £66 million and went in loan guarantees five UK companies.82 Another UK company, Sir Alexander Gibb and Partners (now known as Gibb Limited), which received EU grants, is also charged.83

63. The charges laid before the Lesotho courts are detailed and rest on bank records provided by the Swiss authorities. In the case of Balfour Beatty, it is alleged that, in March 1991, the consortium of which it is a part84 allegedly paid £585,000 via an intermediary into a Swiss bank account controlled by a Lesothan official. Only one month earlier a building contract was signed, worth £135 million. In March 1994, the consortium allegedly paid another £200,000 to the official's account. Two weeks later, they signed the contract to build another dam, worth £41 million. Altogether the consortium - the Lesotho Highland Project Contractors - allegedly handed over one million pounds.85

64. Good governance and due diligence might suggest that the ECGD should have vetted the corruption records of the companies prior to offering them support. The Corner House has seen no evidence that either the ECGD or any of the other agencies involved in financing the project ever did so.86 Even today, there is no binding requirement for the ECGD to undertake such a vetting process of the companies to which they award contacts nor of their associates in any consortium of which they are part.

65. Such lax procedures indicate a major governance failure. In the Lesotho case, for example, most of the companies now in the dock - charged with passing some £2 million in bribes to a key official in order to win the contracts for the project - are no strangers to allegations of corruption: for the ECGD not to have taken account of this in deciding to become involved in the project suggests, at best, a cavalier attitude to corruption, at worst, gross irresponsibility in its handling of public funds.

66. For example, Balfour Beatty had earlier been involved in the Pergau dam scandal, where allegations of corruption were rife (see Appendix 1). Its partners in the Lesotho Highland Project Contractors include France's Spie Batignoles, which, according to Balfour Beatty, was the lead finance company for the Lesotho contract.87 Spie Batignoles was involved in Kenya's Turkwell Gorge Dam which, because of bribes reportedly paid to Kenya's president and energy minister, cost more than twice what the European Commission said it should have cost.

Both Keir International and Stirling International, meanwhile, are partnered with the Italian construction giant Impregilo in the Highland Water Venture. Impregilo was one of the three principle firms involved in the Yacyreta Dam in Argentina and Paraguay, which Argentina's President Carlos Menem called "a monument to corruption". Impregilioalso had contracts on Guatemala's Chixoy Dam, a project in which between $350 and $500 million was lost to corruption.88

67. Regardless of the outcome of the Lesotho trial, the ECGD should show how it justifies having lent its name - and public money - to members of consortia whose partners' past behaviour and practices were so suspect.

68. The Committee may also wish to inquire why the ECGD continued to support the project - including new credits to the consortium of which Balfour Beatty is a part89 -after the Lesotho authorities first uncovered evidence of financial mismanagement.90 Indeed, by the time the second tranche of credits went through, Masupha Sole, the head of the project who is alleged to have taken bribes, had already been suspended for a period whilst the project's accounts were investigated.

69. There is also concern that the ECGD is not as rigorous in its scrutiny of the contracts it underwrites as the public has a right to expect. In 1990, for example, the ECGD backed 85 per cent of a £38.1 contract awarded to consultants Knight Piesold for undertaking the feasibility and environmental impact assessments for the Ewaso Ngiro dam in Kenya. The project was already tainted with allegations of corruption against Energy Minister Nicholas Biwott. The ECGD's due diligence procedures would appear to have revealed no suspicious elements to the contract.

70. By contrast, the World Bank, which investigated the project, criticised Knight Piesold's fee as being "five times what such services would normally cost".91 Moreover, according to the Bank, at least £15.3 million had been paid up front to Knight Piesold, even though the project was not due to come on stream for another 10 years. "The exorbitant cost of this contract together with the high level of upfront payments ... even before the feasibility study had been completed, raises fundamental questions about procurement practices and financial management", stated the Bank's report. Knight Piesold said at the time that the "fee was entirely in line with the norm for work of this nature." The firm later went on to win contracts for "full tender design and documentation" and is still working on Ewaso Ngiro, with ECGD backing.92

71. The Corner House believes that the ECGD lending on both the Lesotho Highland Water Project and Ewaso Ngiro suggest sufficiently lax governance procedures to merit a National Audit Commission investigation as to whether the public's money was put at undue risk or was misspent.

Oversight of Commissions

72. The Corner House is also concerned that the procedures for vetting "commissions" included in the contracts underwritten by the ECGD are inadequate. Commissions are frequently a euphemism for bribes channeled through agents by companies. A survey by Control Risk Group of business development managers showed that 56 per cent of European companies surveyed said they "occasionally" used middlemen to avoid direct involvement with corruption and 44 per cent agreed it was a regular occurrence.9394 If the agent is caught having bribed an official, the firm simply says it paid a traditional commercial 'finder's fee' to the agent and had no way of knowing what the agent did with the money.95

73. Given this widespread corruption in the use of agents, Transparency International has described the practice of underwriting commissions as "an indirect encouragement to bribe" and "close to complicity with a criminal offence."96 UK taxpayers, who are ultimately responsible for any losses incurred by the ECGD,97 may also question whether the underwriting of bribes - even unwittingly - is a use to which public money should be put.

74. The size of a commission fee is often a good guide to determine whether the agent's role was legitimate or not. A fee in the amount of 3-5% of the contract value may well be legitimate: a fee in the amount of 20% of the contract value suggests strongly that one is dealing with bribe money.98 Currently, the ECGD scrutinizes the size of commissions and action is taken when a commission is higher than generally accepted for the service provided. Where projects are underwritten by a number of agencies, ECGD does not, as a matter of course, see the application forms completed by their exporters. However, the ECGD confirms that "if we had concerns over excessive commissions on the UK element, it would be open to us to make enquiries of others."99

75. These procedures are too limited in scope to prevent corruption. Although the ECGD's primary concern should be to ensure that excessive commissions are not underwitten in the UK element of a project, it also has a wider responsibility to ensure that the project as a whole does not involve corruption. Simply ensuring that the UK has clean hands is not enough, since the UK's involvement in the project may be critical to the project going ahead - and therefore to bribes involving the "non-UK element" being paid.

76. In addition, the ECGD procedures do not require the ECGD to investigate the agents being used by companies. In the Lesotho case, the prosecution has alleged that the middleman who paid Sole was a Frenchman called Max Cohen. Cohen's company is registered in Panama, a country notorious for laundering money.100 This alone might have alerted the ECGD to the possibility of corruption - had the agency investigated Cohen's company background. Significantly, World Bank staff, discussing corruption in Indonesia, have stated that, in their view, the rigorous scrutiny out of agents through stringent "prequalificant" requirements constitutes "the single most important reform" which the World Bank could undertake to deter corruption (see World Bank Memorandum reproduced in Appendix 2).101

Failure to Alert the Investigating Authorities

77. The Corner House is also concerned that, even in cases where evidence of corruption in ECGD-backed projects is alleged, the ECGD is singularly resistant to undertaking independent investigations or even to conducting internal investigations.

78. In the case of the Lesotho Highlands Water Project, for example, the ECGD initially appears to have taken no steps to scrutinize the detailed evidence presented to the Lesotho court in the charge sheets against the companies. Indeed, when the charges were first laid, the ECGD initially denied that Balfour Beatty was even being prosecuted (a position it justifies on the grounds that although the charges had been filed, the case has still to come to court). As of June 2000, a full five years after the Lesotho authorities first began their investigation into financial mismanagement in the Lesotho Highlands Water Project, the ECGD had apparently made no inquiries to the chief prosecutor in Lesotho; and its own inquiries when the allegations against the companies were first made public appear to have ended when assured by Balfour Beatty that no wrong doing took place.

79. Demands from non-governmental organizations that the company be suspended from applying for other credits pending further investigations (it is currently seeking one for the equally controversial Ilisu Dam) have been rebuffed. In a letter to The Corner House and other NGOs, Trade Minister Richard Caborn states:

"Your letter raises the issue of various allegations of corruption and fraud which have been made against companies associated with Balfour Beatty and consortia and joint venture companies in which Balfour Beatty companies are or were participants. As you acknowledge in your letter, the allegations against these consortia/joint ventures have yet to be proven. We consider that the principles of natural justice, to which you also refer, require that Balfour Beatty companies should have the benefit of the presumption of innocence and we therefore do not envisage suspending current applications pending a resolution of the investigations/court proceedings.

You have asked that a UK investigation of the allegations and of the company's corporate governance structure should be initiated. The allegations in Lesotho ... are being investigated by the competent authorities in those countries and we will of course co-operate with them should they request assistance from the UK. At present, however, we do not intend to initiate a separate investigation in the UK."102

80. The Corner House rejects this reasoning. Under the UK Prevention of Corruption Act 1906, it is an offence to bribe a foreign official in order to obtain a contract.103 It is not for the Minister of State but the police and the UK judicial authorities to decide whether or not the evidence presented to the Lesotho courts is sufficient to merit an investigation into possible infringements of UK law.104 Nor should such an investigation be dependent on the outcome of the Lesotho case. If there are good grounds for suspecting that the law may have been broken, then the UK authorities have a duty to investigate. Whether or not criminal proceedings follow would depend on the decision of the Attorney-General or the Solicitor-General. The Corner House is unaware, however, of any action having been taken to report the allegations to the Director of Public Prosecutions under the 1906 Bribery Act.

81. The Corner House further notes that, in the view of the Organisation for Economic Cooperation and Development (OECD), a conviction of the company representatives alleged to have paid the bribes would not be a prerequisite for finding the companies criminally liable under UK law: the outcome of the Lesotho trial is, in this respect, irrelevant.105 Moreover, the Government's own stated policy on corruption is at variance with Mr Caborn's view on the presumption of innocence (a view with which the Corner House has considerable sympathy). As the Home Office states in its June 1997 statement on "The Prevention of Corruption":

"Reversing the burden of proof in criminal cases is a serious step to take and requires full justification. In circumstances where a person is expected to exercise impartial judgment, it is arguable that that person should order his or her private affairs in such a way as to avoid any impression of corrupt activity. It may be reasonable therefore to expect a person in these circumstances to justify any questionable payments made to them. The Government therefore believes that it is right to consider carefully an extension of the presumption of corruption."106 [Emphasis added]

New Anti-Corruption Rules

82. Recently, the ECGD introduced new rules aimed at ensuring that "corrupt activity goes unrewarded".107 The new rules stipulate that companies must sign a declaration that neither the exporter nor anyone acting on its behalf has engaged in any corrupt activity and will not engage in any such activity.108

83. Whilst this is a welcome move, The Corner House notes that it will do little to address the procedural and institutional failures that have led to many allegations of corruption to date.

83. In addition to new rules - and accompanying staff incentives that reward their implementation - to encourage thorough investigation into backgrounds of companies and their associates, the ECGD should:

  • Introduce a mandatory requirement to withdraw credits awarded to companies convicted of corruption, regardless of whether or not the conviction is directly related to an ECGD credits or guarantee;
  • Suspend credits (or the consideration of credits) where a company receiving or seeking ECGD support is being investigated for corruption, pending the outcome of the inquiry;
  • Refer all allegations of corruption that involve UK companies bribing foreign officials to the police and instigate their own independent inquiries;
  • Ban any company found guilty of corruption from receiving ECGD support for a period of ten years.
  • Liaise with other export credit agencies and multilateral development banks to draw up a consolidated list of companies banned by any international finance institution.

Corporate governance, corruption and the UK private sector

85. UK private sector involvement in corruption comes in many forms - from bribery of officials to win contracts to the handling of corrupt payments by UK banks.109 The evidence suggests that bribery is more common than the relatively low number of court convictions would suggest.110

86. A number of major UK companies involved in infrastructure projects in the South have recently been linked to corruption allegations that have resulted in investigations. These include: PowerGen (Paiton II Power Project, Indonesia); Balfour Beatty (Pergau Dam, Malaysia; North East Corridor Rail Modernisation Scheme, USA; Lesotho Highland Water Project, Lesotho; Singapore); AES Ltd (Bujagli Hydroelectric Project, Uganda); Sir Alexander Gibb and Partners (Lesotho Highlands Water Project, Lesotho); Keir International (Lesotho Highlands Water Project, Lesotho); Sterling International (Lesotho Highlands Water project, Lesotho); Knight Piesold (Ewaso Ngiro, Kenya).

87. Details of these allegations are appended as Appendix 1. Details of the involvement of UK banks in corruption are provided in a Corner House briefing, submitted to the Committee as a background document.111

88. Many have resulted in official investigations by the relevant national authorities and, in some cases, to court proceedings being initiated against the companies involved. The Corner House accepts that the allegations have yet to be proven but submits that, regardless of the outcome of any pending investigations, the very fact that the allegations have been made raises important question marks over the current culture and corporate governance of the companies involved, in addition to highlighting gaps in UK company law, which are of relevance to the Committee's inquiry.

These concerns are outlined below.

Institionalised Racism and the Culture of Corruption

89. Underlying much bribery by Western companies of Southern officials is a view that bribery is the way one does business in the South. Illustrative of this view is a letter recently published in The Daily Telegraph:

"Having been involved in exporting to various countries in the Middle and Far East and in Africa, I have bribed government ministers and officials of all grades, in the form of cash payments, commissions, introductory fees, new cars, hotel accommodation, provision of hospital treatment and so on for more than 40 years. If I were not now retired I would continue to do so. That is the way one does business in those places, and in conforming to such customs I, like many others, have earned this country many millions of pounds in foreign exchange ... while ensuring the gainful employment of several thousands of my fellow countrymen and women."112

90. Such "explanations" not only obscure the role that Southern governments and popular anti-corruption movements have played in exposing corruption in the South,113 but also the role that Northern businesses and governments have played in creating a "bribe culture". As Dieter Frisch of Transparency International notes: "I do not know of a single place on earth where growing rich through taking bribes is considered lawful or morally acceptable." He goes on to quote Olusegun Obansanjo, former President of Nigeria: "In the African conception of appreciation and hospitality, a gift is a token. It is not demanded. The value is in the spirit of the giving, not the material worth. The gift is made in the open for all to see, never in secret. Where the gift is excessive, it becomes an embarrassment, and is returned. If anything, corruption has perverted the positive aspects of this age-old tradition."114

91. The Corner House believes that corruption will continue to flourish so long as the myth of "the Third World culture of corruption" remains unchallenged. In particular, measures - along the lines recommended by the Macpherson Committee - are urgently needed to address the institutionalised racism that underpins such views.

Failure to Inform Shareholders

92. Corruption tells investors a great deal about how a company is run and the competence (or otherwise) of its management. Under the Companies Act 1985, company directors are required to prepare financial statements for each financial year which give a true and fair view of the state of affairs of the company. Many companies, however, appear to take a narrow interpretation of this duty when it comes to reporting corruption allegations, even where those allegations have resulted in prosecution or in action being taken by the local authorities.

93. In the case of Balfour Beatty, for example, no mention is made in its 1996 Annual Report of the Singapore government's decision to ban the company from bidding for contracts for a period of five years. Similarly, the company's 1999 Annual Report115 and 2000 Interim Report116 both fail to mention that the company is being prosecuted for corruption in Lesotho, as part of the Lesotho Highlands Project Contractors consortium. Yet charges, which were laid against the company in December 1999, could have severe financial repercussions for the Balfour Beatty: for example, non-governmental organisations are calling on the World Bank to any convicted companies from bidding for World Bank contracts.

94. In other instances, the information that is supplied to shareholders on projects where corruption is an issue is often misleading. PowerGen, for example, has a 35 per cent stake in the Paiton II power plant in Indonesia. Following the SE Asia economic collapse and the fall of President Suharto, the Indonesian State Electricity - PNL - has alleged that many of the power purchasing agreements it had signed with independent power producers were corruptly negotiated and, in some cases, it has refused to honour them. A focus of PNL's investigations has been the Paiton contracts.117 PowerGen's 1999 Annual report, however, gives no indication of such corruption allegations. Instead the report refers only to PNL's "short-term difficulties in meeting their contractual obligations as a result of the financial crisis in Indonesia."118 It does not state what shareholders most need to know: namely, whether or not the Paiton II contract is one of those being challenged by PLN.

95. The failure to disclose corruption allegations to shareholders is of major concern and signals a major lacuna in current standards for company reporting.119 Corruption is not only damaging to a company's reputation, but is also indicative of poor management control within a company. Shareholders are responsible for appointment of board members and, ultimately, for the management of the company. If they are to fulfill those responsibilities, they need to be in a position to judge the integrity of management personnel and corporate governance structures. Full disclosure of all information relevant to making such an assessment - including the outcome of any internal investigations into corruption allegations - is thus essential.

96. Such extended reporting would be in line with the recommendations of the Turnbull Report, undertaken by the Institute of Chartered Accountants for the Stock Exchange. The report recommends that companies should report annually on the steps they have taken to institute internal controls for managing all risks to their businesses, including non-financial risks. Anti-corruption would, in The Corner House's view, fall within the remit of any such report.

97. The review of company law currently being undertaken by the UK government offers an opportunity to introduce measures that would require companies to disclose corruption allegations - and measures taken to counter corruption - to shareholders. The Corner House recommends that the UK government should introduce legislation to correct this gap in current company law.

98. The Corner House also recommends that companies be encouraged to draw up ethical policies laying down anti-corruption standards against which shareholders and investors can judge their performance and thus the integrity of their corporate governance structures. A number of companies already have such policies in place.

Little Fear of Prosecution

99. The pervasive use of corruption by Western companies operating in the South also reflects the relaxed attitude of Western legal authorities towards corruption.

100. In the UK, there has not been a single prosecution of either an individual or a company for bribery of a foreign public official.120 This is despite legislation prohibiting such bribery being on the statute book since 1906.

101. Investigations into corruption are similarly hampered by the authorities' reluctance to pursue corruption. Prem Sikka, Professor of Accountancy at Essex University, has stated that he experienced 'a total block' in getting evidence looked at by government over the last ten years about a money laundering scandal involving British-based accountancy firms. "The reluctance of regulatory authorities to investigate evidence and allegations brought out in this case indicates an alarming degree of inertia and buck-passing within the UK regulatory process."121

102. Although the Government has recommended changes in the law that will make prosecution for bribing foreign officials easier, the new rules will mean little without strengthening the government's investigative arm. The Department of Trade and Industry, however, has turned down proposals to set up an anti-corruption office, arguing that it is not the role of the British government to monitor behaviour of UK companies overseas. Effectively, this means that no-one will be responsible for ensuring that UK companies are held accountable to the new law.

Corruption and the wider policy environment

103. Although tightening procedures and instituting stricter internal controls and staff incentives and penalties aimed at reducing the opportunities of corruption are critically important, these measures are frequently undermined by the broader macro-economic policies which Britain, through the World Bank and the IMF, encourages: economic liberalisation, deregulation, privatisation and structural adjustment.

103. By undermining the political credibility and regulatory capacities of many states, liberalisation, for example "has contributed to a more generalized process of political decay. This reduces the incentives for probity on the part of officials and politicians, and creates a widespread social alienation from the political process".122 Regulatory mechanisms have been weakened; there is no longer any need to provide economic justification for money transfers; and it has become far easier to exchange and transfer currencies and capital.

104. Likewise the rapid privatisation of public services - a condition of structural adjustment loans - has increased the opportunities for corruption. State enterprises have often been privatised before workable frameworks for regulation have been set up. As a result:

  • Governments often cannot arrange transparent and open bidding processes or promulgate needed regulatory laws;
  • Managers and employees, fearful for their future and confident of their ability to escape punishment, commonly strip the assets of the entities undergoing privatisation;
  • Interested parties engage in insider dealing and political manipulation of the process for their own profit;
  • Many state enterprises do not have the time to become economically viable before being sold off, leading to frequent sales of industries at below market value despite heavy government spending on recapitalisation.

105. Civil service reform - in practice downsizing - has similarly eroded governance. At the same time, wages for civil servants who remain employed have declined because of SAPs, resulting in a lack of motivation, low morale, and increased risks of petty corruption.

106. NGOs in the South and North are thus calling for the World Bank and IMF to:

  • Ensure that the privatisation programmes they impose include provisions for appropriate and robust regulatory frameworks to be put in place before privatisation is begun;
  • Examine public sector reforms which do not involve privatisation, particularly in sectors such as water and health, in which services to vulnerable groups cannot be provided at a profit;
  • Review whether loans made towards privatisation would be more effectively spent on administrative reform of the entities to be privatised;
  • Draw up a plan of action to encourage accountability and transparency in privatisation programmes;
  • Shift their emphasis away from downsizing towards more long-term solutions;
  • Help governments make a concerted effort to ensure that civil service salaries are raised;
  • Help governments increase accountability of the civil service through more training, freedom of information legislation, whistle-blower laws, and punishment for wrongdoers.

103. The Corner House believes that deep institutional changes are required in both the private sector and the public sector if Britain is not to continue underwriting, both socially and financially, corruption in development projects.

104. The Corner House therefore recommends that:

  • The Government publish details of steps taken to address the long-identified institutional failures in UK-backed agencies such as the ECGD, the World Bank and and other international finance institutions, with specified time lines for action;
  • The Government forward the details of corruption allegations in the Lesotho Highlands Water Project to the relevant UK law enforcement authorities with a view to investigating whether or not a breach of UK law has occurred. The ECGD should also be required to undertake a full investigation;
  • The ECGD and other public bodies cooperate with the World Bank in drawing up its proposed consolidated list of companies found guilty of corruption with a view to debarring them for a specified period from access to UK public funds;
  • The government consider changes to UK company law with the aim of requiring companies to report to shareholders on all allegations of corruption, together with an assessment of the likely impacts on the company's bottom line and reputation;
  • The ECGD review its debt portfolio with a view to canceling debts incurred through corruption.

105. Given the vast sums of UK taxpayers' money and jobs that would appear to have been lost to corruption through poor corporate governance of both international and national public sector agencies involved in financing development projects, The Corner House urges the Committee to recommend that the government institute a National Audit Office review of programmes and projects where allegations of corruption are well-founded. The World Bank's loans to Indonesia and the ECGD's export credits to Kenya and Lesotho are cases in point.

106. The Corner House would like to thank the Committee for its consideration of these issues and hopes that this memorandum will aid the Committee in its deliberations.


Appendix 1: Recent cases of corruption involving UK companies and UK-backed International Financial Institutions

Turkwell, Kenya

UK Company Involvement: Knight Piesold

UK Government Involvement: Export Credits Guarantee Department

Between 1986 and 1993, Knight Piesold was "overview consultant for detailed design and construction" for the 155 metre-high concrete Turkwell hydropower dam in Kenya - a $300 million project. Knight Piesold documents obtained by The Corner House state the funding for its involvement in Turkwell came via the UK Export Credits Guarantee Department (ECGD), which was not publicly reported at the time.

Other companies involved in the dam included GE Alsthom, Norconsult and Sogreah. Spie Batignolles, the French construction company, won the construction contract which did not go out to competitive tendering.123

In March 1986, an internal memorandum written by Achim Kratz, then European Commission delegate to Kenya, was leaked to the Financial Times.124 The memo stated that the contract price was "more than double the amount Kenya's government would have had to pay for the project based on an international competitive tender." The memo continued, "The Kenyan government officials who are involved in the project are fully aware of the disadvantages of the French deal ... but they nevertheless accepted it because of high personal advantages."125

Kenyan observers say that these "personal advantages" included payments of millions of dollars to Kenya President Daniel Arap Moi and to the then Energy Minister Nicholas Biwott.126 When the dam was completed in February 1991, the Kenyan press described it as "the whitest of white elephants" and a "stinking scandal".

For two-and-a-half years after completion, the dam operated at less than half its designed operating capacity and when it was officially opened by President Moi in October 1993, the reservoir was less than a quarter full.

As a result of the corruption scandal surrounding the Turkwell Gorge project, international donor aid to Kenya's energy sector was frozen for a decade and only began to return in late 1996.127

Ewaso Ngiro

UK Company Involvement: Knight Piesold

UK Government Involvement: Export Credits Guarantee Department

Since 1989, Knight Piesold has continued to be involved in a dam project run by the state-owned Kenya Electricity Generating Co. called the Ewaso Ngiro project - three dams, generating 180MW of electricity and costing a total of $350 million by the project's due completion date of 2007. In 1992, a World Bank study team criticised a £38.1 million contract for feasibility studies and environmental impact assessments that the company won in 1990 for being "five times what such services would normally cost".128

The World Bank's report was obtained by the Financial Times, which reported that the UK government's ECGD had backed 85% of Knight Piesold's fee. The reputation of the client, then called Kenya Power and Lighting Corp, was already tainted by allegations of corruption and other criminal offences against Energy Minister Nicholas Biwott - including accusations that he was one of two prime suspects in the murder investigation of Foreign Minister Robert Ouko killed while investigating high level corruption. Biwot was arrested, then released for lack of evidence. The World Bank documents stated that at least £15.3 million had been paid up front to Knight Piesold, even though the project was not due to come on-stream for another 10 years. "The exorbitant cost of this contract together with the high level of upfront payments ... even before the feasibility study has been completed, raises fundamental questions about procurement practices and financial management," the World Bank report said. Knight Piesold said at the time that the "fee was entirely in line with the norm for work of this nature". Since this scandal, Knight Piesold won further contracts for "full tender design and documentation".

The three-dam project links the Ewaso Ngiro and Amala rivers with a 3.5 kilometre-long tunnel, reversing the Amala's flow which will "consequently suck water from Masarua Swamp", giving Kenya the ability to tap water from the rainy West to the arid Rift Valley. The Masarua Swamp is a key water resource within the famous Serengeti National Park.

The project is causing massive controversy between Kenya and Tanzania, according to a March 1999 report from Mishael Ondieki at The Nation newspaper in Kenya. "Tanzanians are convinced that the formation of dams in Kenya will drain water from Tanzania, leading to migration of animals from their country," Oneiki quoted one source saying. It is predicted that the project, if commissioned, could jeopardise the East African Cooperation regional alliance. Other sources told Ondieki that Tanzania, teaming up with Uganda, wanted to stop Kenya generating power so as not to threaten Tanzanian power finding a market.

The Nation said that Knight Piesold had recently prepared a report claiming that the project was viable and would have "little impact on the environment". However, the report went on to state that it was unable to give conclusive results because of insufficient data on the levels of the Ewaso Ngiro river and Lake Natron into which the river drains. "'It is increasingly difficult to carry out Kenyan research on Lake Natron since it is on the Tanzanian border'," the newspaper quoted the Knight Piesold report.

Knight Piesold also spoke to Tanzanian fears about fragile flamingo nesting and breeding sites being destroyed: "It will definitely affect the flamingo nesting areas but will not at any point hinder them from their breeding grounds since the lagoon there they breed will not be affected." Tanzania has twice vetoed the project, fearing the Masarua Swamp in the Serengeti will be drained, driving wild animals permanently to Kenya.

The Kenyan government is pushing the project; its permanent secretary in the Ministry of Energy, Crispus Mutitu, accused the media of giving the project bad publicity, adding that the country's electricity supply would worsen if the project was not undertaken. The government will have to pay 30% of the total cost of the project under World Bank arrangements - conditions that it has failed to meet on several past projects, which have consequently stalled.15

Yacyreta Hydroelectric Project, Argentina

Itaipu Hydroelctric Project, Brazil

UK Government Involvement: World Bank

Both the World Bank-funded Itaipu Dam and the Yacyreta dam on the Parana River have been beset by corruption allegations. Brazilian journalist Paulo Schilling and Para-guayan ex-legislator Ricardo Canese have described the building of Itaipu as 'possibly the largest fraud in the history of capitalism'. Itaipu was originally projected to cost some $3.4 billion, but skim-offs by the military rulers of Paraguay and Brazil and their colleagues contributed to the cost skyrocketing to around $20 billion." Meanwhile, the Yacyreta dam was famously described by Argentinian president Carlos Menem as a "monument to corruption".

Impregilo and Dumez led a joint venture as main contractor. Lahmeyer International was the second company in the 10-company consortium responsible for the engineering and construction supervision, called CIDY. Harza was the lead company in CIDY. Voith Hydro and Dom. Eng. Works manufactured 13 of the turbines and Impsa and Cometarsa the remaining seven. Voith did the hydraulic design for adjustable blade units, and Voith and GE Canada the mechanical design. Siemens supplied generators (with Ansaldo, Mitsubishi, Hitachi and Toshiba). Impregilo assembled the turbine-generators on site (with CIE, Sade and Iglys).

The Yacyreta dam's costs soared from an original estimate of $2.7 billion to $11.5 billion, and the still unfinished dam is currently 10 years behind schedule. It has faced technical, financial, social and environmental problems. Three turbines had to be taken out of service in 1998 at a cost of $5 million in lost production when cracks appeared. In May 1999, four turbines failed and the binational operating company, Entidad Binacional Yacyreta (EBY), is seeking damages from the manufacturers of $200,000 for each day the turbines are inactive.

The floodgates of Yacyreta's reservoir were closed in 1994 before a detailed environmental and social mitigation plan was in place. The reservoir has never been filled to its full capacity and the dam is operating at only 60% of its installed capacity, below the project's financial break-even point. Financing has not been found for the $857 million worth of additional construction work required to fill the reservoir, nor for past and future resettlement and environmental mitigation costs.

The project was economically justified on the assumption that Argentinian electricity demand would increase by 8-10% per year during the 1980s. In fact, demand grew by around just 2%, so that when the first turbines came on-line in the mid-1990s, Argentina already had a surplus of generating capacity. The World Bank Performance Audit Report says: "Based on the foregoing, the Audit concludes that Yacyreta was not a least-cost solution to expanded power supply and its relevance to the country's priorities was negligible. On several occasions, the Bank had good cause for stopping the project before the major civil works were too advanced."

Less than 25% of the 50,000 people who would be forced to move to make way for the Yacyreta's reservoir if fully filled have been resettled so far. The World Bank's Inspection Panel outlines "unsanitary conditions ... in many of the stagnant bays created by the reservoir (which) pose health risks to poor people living in low-lying urban areas." The panel also found that thousands of people have lost their jobs as a result of the dam and have received no compensation. A June 1999 internal report to the Board of the Inter-American Development Bank points out "some serious problems in EBY's dealings with civil society, particularly people affected by the project and organizations that are speaking for them on the Paraguay side, as EBY's institutional credibility has eroded."

The Itaipu dam, meanwhile, has drowned a large area of Atlantic forest, the fastest disappearing forest in Brazil. Many of the 42,000 people displaced by the dam moved to resettlement schemes in Amazonia, with disastrous effects for themselves and for the indigenous peoples and forest of the region. The reservoir has caused the local spread of bilharzia, a debilitating water-borne disease, previously unknown in the area.

Paiton I and Paiton II, Indonesia129

UK Company Involvement: PowerGen Plc, Barclays Bank

Finance for the massive Paiton 1 and Paiton 2 coal-fired power complex in Java, Indonesia, has been guaranteed by a number of ECAs, including JEXIM, US Ex-Im, OPIC and Hermes. The UK's Barclays Bank was one of eight banks which syndicated the loan for the Paiton 1 project and the West Merchant Bank is reported to be heavily involved in financing Paiton 2, with Prudential Assurance providing debt cover for the project. PowerGen, the UK energy utility, has a 35% share in Paiton 2.

The bid to build and run the Paiton 1 project was won by Mission Energy-General Electric, a joint venture which had the backing of President Clinton, former Vice-President Dan Quayle, and such Washington insiders as Ron Brown, Robert Rubin, Warren Christopher and Henry Kissinger.

In December 1998, the Wall Street Journal reported a series of corruption scandals associated with Paiton 1. Members and friends of the Suharto clan, among them Hashim Djodjohadikusomo, a relative of Suharto, as well as Agus Kartasasmita, a brother of the Energy Minister and later Minister for Economic Affairs, had been attributed a 15 per cent stake without payment.130 Djodjohadikusomo and Kartasasmita were also awarded the order to supply coal for the plant, despite their company having no previous experience in the coal business. The contract was awarded without public tendering. The Indonesian National Audit Commission has been estimated that such corrupt contracts increased the cost of Paiton 1 by $600 to $1000 million.

As Peter Bosshard notes, these costs were shifted to the government by charging PLN, the state electricity board, an extremely high price for the electricity it purchased from the Paiton plant. The final electricity tariff was set at 8.6 cents per kilowatt-hour of electricity, 32% higher than comparable tariffs in Indonesia and 60% higher than in the Philippines. ""It was a presidential decision", commented Negah Sudja, a former head of research at PLN, in the Asian Wall Street Journal, "Everybody knew it was nepotism, but we couldn't do anything about it." The President of PLN, Djiteng Marsudi, was more explicit: "The power companies dictated terms to us because they had Indonesia's first family behind them. Resisting them was like suicide."

Ex-Im officials were told by government officials and by PLN staff that they did not want and could not afford the plant, but that they were powerless to challenge the project as it had the backing of the President.

The economic collapse in S.E Asia and the crash of the Indonesian rupiah meant that PNL could no longer meet its obligations under the power purchasing contracts, which had to be paid in dollars. Initially, the Ministry of Mines stepped in but by March 1998, it had run out of funds. The contract was renegotiated but the tariff was not disclosed

With the fall of Suharto in May 1998, the new government announced that it would check all power purchasing agreements for corruption and nepotism. Where this could be proven, the contract would be considered null and void. PLN is focusing its attention on five power plants, including those at Paiton.

In October 1999, PLN filed a suit against the companies that operate Paiton 1 in a move to void the power purchasing agreement. However, PLN was advised by Indonesia's new president, Addurraham Wahid, not to proceed - and the head of its negotiating team, along with the head of the company, were dismissed.

Indonesia's Attorney-General, however, is confident of a prosecution eventually. "We are in possession of unambiguous evidence for corruption. So far, however, we have been forced by political pressure to suspend our investigations until an interim agreement has been been concluded. Once we will be able to proceed with the investigations, it will become clear which companies have been paying bribes."131

Pressure from western governments on PLN to conclude a settlement has been intense. In July 1999, a delegation of the export credit agencies from Switzerland, Germany, the USA and Japan warned ministers that a renegotiation of the power purchasing contracts would have a detrimental impact on inward investment. A refusal to pay "would impair Indonesia and our ability to work with you in the future." In late 1999, the government gave into pressure and withdrew the legal action against the Paiton operators.

Lesotho Highlands Water Project, Lesotho

UK Company Involvement: Balfour Beatty, Kier International, Stirling International, Kvaerner Boving and ABB Generation's UK

UK Government Involvement: Export Credits Guarantee Department, World Bank, European Investment Bank, Commonwealth Development Corporation

Nineteen companies and individuals are currently on trial in Lesotho, charged with paying millions of dollars in bribes to obtain contracts on the Lesotho Highlands Water Project, a massive water diversion scheme intended to bring water from Lesotho to South Africa. Four British firms - Balfour Beatty, Sir Alexander Gibb and Partners, Kier International and Sterling International Civil Engineering - are implicated.

British taxpayers have underwritten loans to UK contractors involved in the project - including those implicated in bribery - to the tune of £66 million.132 Gibb, Balfour Beatty and their partners received EU grants. The EU along with the World Bank are so determined that this criminal trial should be a watershed for international trade that they have offered to pay for Lesotho's prosecution.

According to Swiss bank records, which form the basis of the prosecution's case, the Lesotho Highlands Project Contractors consortium of which Balfour Beatty is a part allegedly paid £585,000 in March 1991 via an intermediary into a Swiss bank account controlled by the Lesothan official in charge of the project. Only one month earlier a building contract was signed, worth £135 million pounds. In March 1994 the consortium allegedly paid a further £200,000 to the official's account. Two weeks later, they signed the contract to build another dam, worth forty one million pounds. Altogether, this consortium alone allegedly handed over a million pounds in bribes.

From its outset, the Lesotho Highlands Water Project was founded on rule breaking - not least rules enshrined in the World Bank's Charter that forbid the Bank from meddling in the internal political affairs of a member country. The project was first conceived during the Apartheid era when South Africa was subject to international sanctions. To avoid the difficulties of international financiers openly aiding the then-apartheid regime, the project's financial advisers - Chartered WestLB - set up a London-based trust fund through which payments could be laundered. It was an arrangement which, to say the least, was of borderline legality - yet it was sanctioned at the highest international level, not least through the Executive Directors of the World Bank (who collectively represent the bulk of the world's governments).

Funding for the project has come from the World Bank; the European Investment Bank; the German, British and French bilateral aid agencies; the UK Commonwealth Development Corporation; commercial banks including Banque Nationale de Paris, Dresdner and Hill Samuel; and a number of export credit agencies (including Germany's Hermes, France's COFACE, Italy's SACE, South Afrikaans's SACCE and Britain's ECGD). The ECGD's support amounted to £66 million and went in loan guarantees for five UK companies, four of which are now being prosecuted. Not one of the financing agencies, however, appears ever to have vetted the corruption records of the companies bidding for contracts.

Although the Bank has instigated an internal investigation into the current corruption, the investigators -Arnold and Porter, a prestigious Washington-based law firm - have reportedly been subject to restrictions. For example, Non-governmental organisations have told by Bank officials that the firm has been denied complete access to World Bank files and is only allowed to copy files which it could have obtained via third parties. This is denied by the Bank. Once completed, the investigation will not be made public.

Meanwhile, demands by NGOs that any conviction in the Lesotho courts should result in the companies being debarred from World Bank contracts, as required under World Bank rules, are being steadfastly resisted. Convictions in the court, the Bank has stated, will have no bearing on the Bank's future dealings with any of the companies.

Instead, the Bank is insistent that it will only disbar companies if its own internal investigations show that a company has been involved in corruption involving a project component specifically financed by the World Bank. Surprisingly, at the Bank's AGM 2000 in Prague, President Wolfensohn publicly announced that the Bank will wait for the results of the trial. Nevertheless it is not clear how the Bank will act in case companies will be convicted under the Lesotho law and not found guilty under the Bank's internal investigation.

In any case, President Wolfensohn made it clear that the Bank will only disbar companies if investigations show that a company has been involved in corruption involving a project component specifically financed by the World Bank. Since the Bank only made a small contribution to the multimillion dollar financing scheme, this would mean that few - if any - companies are affected.

That position is based on the narrowest legal interpretation of the Bank's guidelines and a singularly selective view of the Bank's involvement in the project. Not only did the Bank finance the design of the project: it was also responsible for setting up and coordinating the financing programme. Indeed, in a confidential 1991 World Bank project document, the Bank explicitly states;

"In the early stages of project preparation, the Government of Lesotho explicitly requested that the Bank be the lead agency in the rising of the massive amounts of funds required for implementing the project and in helping to guide the complicated and sensitive negotiations between Lesotho and the Republic of South Africa. That the proposed project has reached its current stage is clear evidence of the Bank having successfully fulfilled this role to date."

Western Ghats Forestry Project

UK Government involvement: Department for International Development

See attached Extract from Comptroller and Auditor General of India's Report.

Bujagali, Uganda

UK Company Involvement: AES Electric Ltd

UK Government involvement: Credit being considered by Export Credits Guarantee Department, World Bank.

The proposal to dam Bujagali Falls is currently before the World Bank, with a decision expected to be reached within six months. If approved the 250MW hydropower scheme will inundate one of Uganda's prime tourist destinations located on the Victoria Nile, a river already modified by the existence of two other large dams - the Owen Falls dam and the Owen Falls Extension. At a total cost of US$520m it is reported to be the largest private investment in East Africa.

The project is a joint venture between the UK's AES Electric Ltd, a wholly owned subsidiary of the US AES Corporation, and the Ugandan company Madhvani International. AES Nile Independent Power, with offices in both Kampala and London, is the company established to oversee the project.

Formal approval for the project by the both the Ugandan government and the World Bank was rejected on numerous occasions; however the Ugandan parliament finally agreed construction in 1999. World Bank concerns over the deal centred on the cost - more than 15% of Uganda's GDP - together with certain aspects of the Power Purchasing Agreement (PPA). Consequently, in 1999, the World Bank instigated a 12 month suspension on signing of the PPA in order for the contract, under which there would be a 30 year power purchase deal with the Ugandan Electricity Board (UEB), to meet it's required guidelines.

Within Uganda criticisms of the project came from government ministers, NGOs and the media. Following allegations of corruption in Uganda Confidential, a letter from three members of parliament, Absalom Ongom, chair of the Parliamentary Committee on Works, James Mwanda, chair of the Committee on Commissions, Statutory Authorities and State Enterprises, and Wandera Ogalo, chair of the Committee on Legal and Parliamentary Affairs, was sent to the then Minister for Energy and Mines, Richard Kaijuka, calling for his resignation. It was alleged that Kaijuka had demanded "a bribe of US$500,000 from Nile Independent officials out of which [he] received US240,000 with the balance to be paid ... after the signing the agreement between Uganda Electricity Board and Nile Independent Power". Kaijuka was subsequently dismissed and replaced by Syda Bumba.

Between 1998 and 2000, police investigations revealed massive embezzlement of AES Nile Power funds, culminating in the arrest of three staff, including the company administrator. The company is reported to have lost over Sh600m through fraudulent practices.

The project has also been criticised for the lack of transparency in the allocation process. As it was not put out for international competitive tendering it is not known how AES procured the contract to build Bujagali.

Madhvani is also being investigated by the World Bank over allegations of corruption and faces possible debarment from World Bank projects.133

Pergau, Malaysia

UK Company Involvement: Balfour Beatty

UK Government Involvement: Overseas Development Administration

The Pergau dam, built on the Malaysian-Thai border with £234 million of British overseas aid, has become a byword for patronage politics and the illegal use of aid money. The contracts for the dam were awarded jointly to Balfour Beatty - a company with close links to the British Conservative Party - and Cementation International, a company which employed the son of the then Conservative Prime Minister, Margaret Thatcher, as an adviser. Balfour Beatty, a major donor to the then-ruling Conservative Party, won civil works contracts for the dam - without competitive bidding. The works included a 75-metre high zoned earthfill dam, power tunnels and shafts, an underground power cavern and a 24 km water transfer tunnel, together with a pumping station.

Britain's aid agency, the Overseas Development Administration (ODA), opposed the funding of Pergau. However, Thatcher made an oral offer to fund the dam during a visit to Malaysia in 1989, conditional on a full economic appraisal. In 1990, an ODA review of Malaysia's power sector identified a number of alternative projects and concluded that Pergau would not be an economic proposition until the year 2005 at the earliest. Nonetheless, the government agreed to fund the project in February 1991. At the time, Alan Clark, the UK Defence Procurement Minister, argued that withdrawal of support for Pergau "would have an adverse impact on UK relations with Malaysia in general and defence sales in particular."

Documentary evidence subsequently revealed that the aid package was linked in writing to a reciprocal arms deal whereby the Malaysian government agreed to buy over £1,000 million worth of British military equipment in return for the UK funding Pergau. A judicial review brought by a British NGO, the World Development Movement, against the Foreign Office led to a High Court ruling that aid for Pergau was in violation of the 1966 Overseas Aid Act, which forbids British aid money being used for the purchase of arms. Conservative ministers in parliament had consistently denied the link between aid for the dam and arms.

Subsequently, the "revolving door" between Whitehall and the City, which has long ensured a place for ex-Ministers and top civil servants in the boardrooms of corporate Britain, saw Sir Charles Powell, Thatcher's foreign affairs adviser until 1990, become a director of Trafalgar House, which owns Cementation. Both Lord Prior, a former minister under Thatcher, and Lord King, ennobled by Thatcher, have also been linked to the affair.17

In July 2000, Gregory Palast of The Observer interviewed barrister Jeremy Carver, an advisor to Transparency International. "I went to a DTI reception. I was introduced to someone who identified himself as the chairman of a company and we were talking about corruption. He announced with enormous pride that he personally had handed over the cheque to the government minister for the Pergau Dam 'bribe' in Malaysia." The corporate honcho, the chairman of Balfour Beatty, was not confessing, but boasting about the payment which he may have considered not a bribe but just the cost of doing business Malaysian-style. Carver noted that the then Tory Trade Minister, learning of the pay-off, publicly congratulated Balfour Beatty on its patriotic competitiveness."134



Appendix 2: World Bank Memoranda On Corruption In Indonesia

Confidential: WB Indon resident staff views re "leakage", Staf Bank Dunia di Jakarta Augustus, 1997

Summary of RSI staff views regarding the problem of "leakage" from World Bank project budgets

(Emphasis Added)

(The following summarizes informal discussions with RSI operations staff, confidential inputs from a small number of contractors and consultants, and the views of the RSI Working Team of experienced project officers; this does not presume to represent the results of a rigorous analysis, rather it is an operational overview of the problem.)

Any review of the problems of budget "leakage" from Bank projects must begin with two unequivocal statements of fact:

1. Documentation of procurement, implementation, disbursement and audits for Bank-financed projects are generally complete and conform to all Bank requirements; we have moved aggressively to resolve each and every irregularity for which we have documents (as well as many cases of preventive action and informal corrections of problems).

2. Bank staff members have not been implicated in any form of misconduct; the Bank, is widely regarded as one of the few "uncorruptable" institutions in the Indonesian development process, but many of our staff (particularly HQ TMs) are viewed as ignorant or uncaring (as in "they don't really want to know") of local practices and thus subject to being misled or deceived rather easily. However, even with these facts established, our projects are being implemented in an administrative culture which is not just tolerant of collusion and diversion of funds, but which blatantly expects civil servants to supplement their incomes by such means; Bank projects are not immune to these practices. One of the difficulties in attemting an analysis of the nature and magnitude of such diversions is the wide range of variation in operational methods among GOI organizations. As described in the accompanying note on "Typology of Informal Payments in GOI Development Projects" (perhaps to be retitled: "A Guide to GOI Worst Practice"), there are a variety of techniques commonly used, but with very different amounts and percentage diversions, by the project officers of GOI agencies. In aggregrate we estimate that at least 20-30% of GOI development budget funds are diverted through informal payments to GOI staff and politicians, and there is no basis to claim a smaller "leakage" for Bank projects as our controls have little practical effect on the methods generally used.

Background

To establish appropriate cultural context for the description of GOI practices, two fundamental facts of Javanese life must be understood: (1) the Javanese social order is extraordinarily hierarchical, requiring respect and deference to those holding higher positions; and, (2) dating from the colonial era, civil servants are paid in two separate components, a base salary and allowances (usually rice, transport, etc.) package, which is only minimally sufficient to cover subsistence requirements, is paid to each employee for simply reporting for duty; any significant task assigned is expected to be renumerated with a separate honorarium or project bonus, which officially is to be budgeted as administrative overhead in each project budget request, but this is not regularly provided, leaving nearly all civil servants in constant search of supplemental income. A common slang expression classifies civil services positions as being "wet" or "dry" depending on the relative accessability of supplemental income. Those assigned to "dry" positions frequently spend most of their days in other forms of employment of all types (e.g. an engineer might "moonlight" for a private developer, an office boy may work as a private courrier, etc.). These practices represent a significant loss to GOI in terms of administrative capacity and efficiency, but are not classified as "leakage" per se.

It must also be understood that the GOI officials occupying "wet" positions, i.e. responsible for administration of development projects or in other positions of significant responsibility, are faced with expectations of income assistance from both higher and lower officials within their work unit. The distribution of diverted funds thus becomes a quite elaborate system in many agencies. Unlike corrupt practices in many other developing counties, the GOI system still expects an acceptable project outcome/result and peer pressures and scrutiny by others in the system tend to limit incomes. (Particularly in recent years, the same cannot be said of higher levels of the structure, and there are serious concerns about the recent erosion of the expectations of quality results.) Another variable in the system is the fact that some GOI officials have been expected to pay for their appointments to "wet" positions (this is frequently reported to be the case in provincial and local governments; e.g. the price of appointment as Mayor of a major city is said to range from Rp. 1 -5 billion), thus some of the diversion must be regarded as a form of cost recovery! The demands of the ruling political faction GOLKAR on their core membership of civil servants in "wet" positions has frequently been cited as a key determinant of leakage, especially during the past two years ahead of the May 1997 elections. Of course, there is an element of simple greed in all parts of the system as well, but it is extremely difficult to determine if a seemingly greedy demand by a senior official is inappropriate or simply a pass-through demand from an even higher level. It is clear that the accumulation of such demands weighs most heavily on projects executed at local government level, where GOI controls are weakest and staff are least willing to question instructions of superiors.

On a more positive note, in those implementing agencies where professional competence and compensation have been improved substantially, and where adequate project management expenses have been brought on budget, the demands for diversion of funds seem to have been quite significantly reduced (e.g. PLN, Telecoms, PGN, and our Health project offices wherein the Bank is financing salary top-ups and other expenses). The primary distortion in these agencies appears to center on firms owned or controlled by senior government officers or their family members seeking to subvert the established procurement processes for major contracts. Of course, it must also be noted that in such large-budget operations (MPW, PLN and Telecoms particularly) even relatively small percentage diversions can total huge sums, but we see no clear pattern of diversion.

While we regard the accompanying "typology" paper as broadly indicative of the patterns and magnitudes of institutionalized diversions of the GOI development budget, the Working Group wishes to illustrate with the foregoing paragraphs the complexity and variability in the patterns of diversion which have to date frustrated any attempt to more precisely quantify or analyse the problem. There are significantly diverging opinions regarding the potential value of attempting to conduct "representive" sampling of projects or contracts, with some members strongly supportive and others feeling it would provide little more than an expanded group of anecdotal cases, but all recognize the difficulty of defining a truly representative subset within the Bank's portfolio. We would welcome the opportunity to discuss this further with you. In addition to the typology/summary, we are also forwarding notes from our Working Team members with the request that they be "for your eyes only". Your request for some examples of Bank projects impacted by these practices is partially fulfilled by these papers; I will prepare a more concise note summarizing the examples if you wish. We will also revise the previous draft note regarding recommended improvements to our procurement processes, and supplement this with other recommended actions to be undertaken by the Bank in cooperation with GOI. The Team would also like the opportunity to meet with you at your earliest convenience to discuss your reaction to this material, next steps and/or additional material you wish us to generate.

GOI Development Budget "Leakage"

Process/Problem Description

All GOI agency budgets are prepared in two parts: (i) routine costs of personnel base, office operations, etc. and (ii) development projects budget including implementation overheads for project design, supervision, etc. However, from the earliest days of the New Order government to the present, the budgets contain only subsistence-level wages for civil servants and grossly inadequate operations and implementation overheads to allow public announcement of inflated figure for development projects investment.

The compensation system for civil servants predates GOI, having been established during the colonial period. Each public employee is paid a subsistence package of base salary plus allowances (typically rice, transport, etc.) from the routine budget, in what may be characterized as a "retainer" for reporting to his/her duty station, then task honoraria or position allowances are to be paid to compensate each employee for work actually performed. The GOI administrative tradition of under-budgeting and/or diverting funds for these supplemental compensation payments leaves essentially all 6 million civil servants being officially compensated at subsistence level only, with the clear expectation that they will find or create means for supplementing their income. In popular slang, GOI agency positions are classified as 'wet" or "dry" based on the relative accessibility of additional income. However, it is a common expectation that persons assigned to "dry" positions will supplement their income (with part-time employment or other activities). The GOI budget process thus assumes the continuation of funds diversion practices.

Most GOI agencies have sophisticated informal systems for diversion of 10-20% of the development budget under their management and for utilizing the proceeds diverted to supplement both their inadequate operations funds and their compensation. These arrangements vary widely among GOI agencies, but almost universally depend on the payment of percentage or lump-sum rebates or "kick-backs" by contractors implementing projects from the agency development budget. Such payments are informal but regarded as an overhead or informal "tax" by most firms doing business with GOI, and are typically included in the unit prices or inflated bills of quantity for the contract. Most GOI agencies demand that quality of project outputs be maintained, although there is concern that attention to quality is being eroded by increasing greed of some managers. The percentage diverted by local government agencies is typically somewhat higher due to generally smaller contract size, as well as additional demand for sharing the proceeds (e.g. often the local military command and/or provincial officials will seek shares). It is difficult to classify this widespread practice as "corruption" in the normal meaning of the word, and there is an important distinction to be drawn between this established process and those cases of embezzlement, fraud, collusion and misappropriation for personal enrichment which constitute actions more typically defined as "corruption". It is suggested that for discussion purposes the budget manipulations be referenced as "systemic diversions", while the non-systemic cases be termed "project diversions" or "criminal activity"; clearly, both types of diversions must be addressed, but differently.

Typology of informal payments in GOI development projects (including world bank funded investments)

(This listing is indicative only, as all parties contributing to this summary have stressed the wide variation in types and amounts for individual projects and implementing units.)

Pre-Project Expenses (5-10% or more of project budget):

  • Payment by project sponsor to BAPPENAS for budget allocation (3-5% or more? Local government project agencies must also pay local and provincial BAPPEDA similar %).
  • For donor assisted projects, payment by project sponsor to BAPPENAS for Blue Book listing (1-2% for listing, more if donor commits financing)
  • Payment by project sponsor to MoF for budget (DIP) release; local governments pay @ for release of INPRES, SPABP, etc. and MoF for subsidiary loans (1-2% or more?) Land Aquisition and Resettlement Costs (extremely variable, but generally "wet"
  • Numerous reports of diversion of 50-80% of funds budgeted for project land aquisition and resettlement assistance, either by production of falsified documents showing higher amounts than actually paid or by use of "middlemen" to aquire land at a low price for resale to GOI at inflated values. Local governments agree undertake much of the land aquisition for central agency projects, only because of the potential for diversion.

Contract Procurement and Award Process (extremely variable, 5-35%. see below):

  • All contractors, suppliers and consultants pay sponsoring agency to be pre-qualified, then pay for place on shortlist of invited bidders (variable, typically <1% of project value)
  • Invited bidders frequently form an arisan (collusion among bidders with predetermined winner who will pay 1-2% to each unsuccessful firm for submission of losing bids) at the suggestion of agency staff or contractors' association - GAPINSI for civil works - (or both). In a typical shortlist of 4-6 firms, payments to arisan members would total 3-1 0% plus GAPINSI fee (2-5%) plus a payment to members of the tender committee (3-7%).
  • Payments to contract signatory and/or GOI project manager, (pimpro) at the time of final award and contract signing (this is the single most variable element the "game" with reports ranging from 0% - for international advisors in several acencies - to 35% or more of contract value in local construction/consulting contracts awarded by some local units. MPW and other central ministries have attempted to limit/control these payments with reported averages of 7-12% for international firms (often paid through local partners) and 12-20% for domestic firms contracts or share of joint ventures; averaging 15% of budget)

Contract Implementation Period:

  • Facilitation payments for required progress reports and invoice processing (1-3%)
  • Commissions to KPKN or other disbursement unit for payment of invoices (0.5-2%)
  • Political contributions and other demands by sponsor and/or GAPINSI (highly variable, but reports indicate many contractors were required to contribute 10% to GOLKAR via GAPINSI within the past year, in addition to demands by local officials; perhaps 2-15%)
  • Business tax collectors are almost always willing to negotiate the tax bill (no net cost to contractor, but loss to GOI revenue of as much as 50-70% of amounts due) Audits and Inspections
  • Staff of BPKP and ministerial or provincial inspectorates are almost uniformly reported to be seeking to find issues or "mistakes" in project implementation which can be "fixed" or ignored in final audit/inspection documents for a fee (variable, from near 0% to 10%)

Other Issues:

  • Delays in GOI contract payments imposes interest costs on contractors (2% per month)
  • Where prefinance funds have been advanced to implementing unit, delays sometimes are the result of Pimpro wishing to collect interest on deposited funds (GOI system very poor in capturing/reporting such project level income or earnings)
  • Substitution of lower quality materials is also a serious problem, but often specifications are not sufficiently tight to allow proper enforcement; bills of quantity are also inflated.
  • Unit prices/billing rates are typically based on recent contract values which include margins for "average" levels of payments as noted above; thus diversion is included.

Classification of GOI Implementing Units by Estimated Magnitude of Development Budget Diversion


Estimated Diversions Agency/Ministry Comments

Relatively Low (less than 15%)

* Relatively small percentages of very large numbers

* Major problems with firms owned/related to senior GOI officials

PLN, PGN, Telecoms, Jasa Marga, Min. of Health? Min. of Mines and Energy


Moderate (15-25%)

Min. of Public Works, Min. of Education, Min. of Agriculture, Min. of Housing/Perumnas, Min of Environment, Min. of Communications? Min. of Religous Affairs? Min. of Tourism, Post & Tel.?


High (more than 25%)

Min. of Home Affairs, including all provincial and local gov'ts. Min. of Transmigration, Min. of Cooperatives & SMEs, Min. of Forestry




Appendix 3: The World Bank

Draft: discussion points regarding improved transparancy in procurement processes

Several potential actions could be taken by the Bank to further enhance the transparency of our procurement processes. However, essentially none of the action options are viable without the full and active cooperation of GOI at very senior levels. The following may, thus, be best viewed as a discussion agenda for exploring with key GOI officials the steps which they may regard as politically and practically feasible for the near- and medium-term enhancement of our mutual procurement transparency.

1 Signifcantly tighten/restructure prequalification procedures for contractors and consultants wishing to participate in Bank-financed projects. In the view of many RSI staff and other participants in Bank projects, the single most important reform or strengthening of our procurement processes would be the serious application of stringent prequalification requirements to assure that only professional, capable bidders can respond to Bank-financed tenders for goods, works and services. This would require only that GOI enforce the prequalification regulations already in place for each implementing agency, although we could offer some suggestions for refining/improving the criteria for assessing and checking the potential contractor/consultant's prior experience claimed (see further on this point below). However, this would imply a major departure from current practice by nearly all GOI offices where now essentially anyone can be listed as a qualified contractor or supplier of any type of goods or works for which the applicant is willing to pay the registration fee. The prequalification process for domestic tenders is largely viewed as a revenue-generation process, rather than a serious screening of the quality of potential contractors. Even for consulting services where shortlists are generally developed for each potential assignment, most implementing agencies regard places on the shortlist as a commercial asset to be sold to the highest bidder with only minimal regard to the actual qualifications of potential consultant organizations. Three (3) additional steps could also be taken to assure the quality of potential contractors, suppliers and consultants for Bank-financed project implementation, as follows:

a. Develop procedures to identify firms owned/controlled by GOI officials or their family members at all levels of government, and proide all Bank project implementing agencies with a "negative list" of such firms not eligible to participate in the procurement process. This would obviously be a difficult and sensitive matter which would also require substantial continuous effort to keep updated, but may help to avoid many of the most serious distortions of the procurement process.

b. Place on the "negative list" for Ban-financed procurements all GOI-owned or sponsored firms (e.g. the MPW "Karya" contractors and consultant firms, DKI?s partial ownership of Pembangunan Jaya, firms affiliated with BPPT, etc.) Again, this would be a very contentious matter with the GOI agencies involved, but would remove the source of some significant past distortions in our procurement process.

c. Expand outreach and information activities, and streamline the procedures for international contractors, suppliers, and consultants to prequalify and participate in Bank-GOI tenders by all implementing agencies (perhaps including a "one-stop" prequalification clearinghouse (at Ekkuwasbang?) for international firms to register their capabilities and routinely receive notification of all tenders by any GOI implementing unit in their fields of qualification) to intensify competition. While the Bank could assist in the development of such procedures, it is quite likely that bilateral assistance, professional organizations and others would be quick to respond if GOI announced its intentions and requested assistance in this regard.

2. Advise GOI that the Bank will not routinely-finance works tendered as "reserved-far economically weak contractors" (typically Class C Qf the standard GOI prequalification system). These small contracts with weak contractors have been one of the most consistently problematic areas of the Bank's implementation portfolio. To the extent practical within each project, implementing agencies should be required to package civil works and gods into tender packages large enough to attract the more capable Class A and B contractors, with Bank financing offered for smaller packages only on an exceptional basis. (Note: Many GOI units also use this provision to limit potential contractors and suppliers to "pribumi"-owned business, excluding firms owned by Chinese Indonesians; this practice cannot continue to be condoned by the Bank.)

3. Modify composition and role of the tender committee to include independentmembers drawn from the communitly (local universities, targeted beneficiaries, NGOs or other appropriate project participants), perhaps even as a majority of membership, and expand to role of the committee to include all tender steps from contract package definition, through distribution of documents and evaluation of bids, to award and contract signing. The details of such a major modification to GOI tendering process would require serious discussion with GOI but could result in significantly changing the current decision-making structure. The key would lie with having truly objective and independent members appointed to the committee, which raises the obvious question of who would make the appointments. Would the Bank wish to have NOL review of the membership? The GOI would surely object.

4. Require wide-circulation newspaper advertising of all tender opportunities, provision of tender documents to all interested parties, and evaluation of all bids received from any qualified contractor/supplier (i.e. eliminate the common practice of restricting tenders to an invited shortlist of prequalified firms). This should produce a larger number of bids for each potential contract, which would clearly complicate the work of the tender committee, requiring additional time and budget for their work (the reason most commonly given for restricting the tender to invited firms).

5. Remove the contractors? association (GAPENSI) from any role in the tender process and agressively discourage the -formation of contractors cartels ("arisan ").

Current practices of posting tender announcements at GAPENSI offices as a primary form of tender advertising and consulting GAPENSI regarding the listing of invited tender participants, simply encourages the formation of "arisan" to rotate awards of contracts among a fixed set of firms, thus circumventing the intended open competition and allowing price-fixing to become commonplace. GAPENSI is also reported to be a primary mechanism of contractors' inappropriate access to budget and owner estimates. While the potential usefulness of GAPENSI in the prequalification process for civil works contractors is obvious, extending their (informal) role into the tendering process is clearly a serious problem to be addressed. The linkage of GAPENSI to the political system cannot be ignored, nor can the influence of GAPENSI on key appointments.

6. Insert the newly developed Bank anti-corruption clauses in all Bank- financed tender documents and open a confidential channel for reporting violations of tender procedures to the Bank-GOI prior to the award of contracts. Too frequently the Bank hears of alleged irregularities only after contracts have long-since been awarded and construction or other services performed, when our range of potential action is limited.

7. Develop performance evaluation sysutem for all Bank (or GOI) contractors and exclude poor performers (negative list) from future tenders. See companion paper on more general implementation process improvements, including audits!!!

Options for Bank-GOI action to reduce development budget "leakage" (discussion draft only)

1. Based on intensive consultation with very senior GOI officials, develop an agreed anti-corruption action plan (ACAP) along the lines suggested in the Bank HQ Working Group report entitled "Helping Countries Combat Corruption: The Role of the World Bank Group". Such an action plan could include agreed initiatives from the menu noted below, as well as initiatives already underway by GOI and further ideas arising from our dialogue.

2. Particularly in light of the need to bring "on budget" at least parts of the informal remuneration now being paid to civil servants from the proceeds of the budget diversions, and the potential macroeconomic benefits of improved systems of governance, we may wish to use the possibility of Governance Improvement Adjustment Loan to focus the required attention of senior GOI policy-makers. Such an adjustment program could include broader civil service reforms and streamlining of GOI structure and procedures, in addition to implementation of the ACAP. I suspect that having a possible $400-500 million (or more) in play may focus their attention on real action options, more than a CPPR-type discussion of problems and actions. Such an adjustment operation could also explicitly support the accelerated privatization of additional BUMNs and BUMDs/PDAM including at local level markets, slaughterhouses, transport terminals, et al.

3. Implement an aureed tightening of Bank-GOI procurement processes, along the lines of the separate note on options for this tightening. However, for "problem units" (i.e. where diversion is known/suspected to be particularly high), including-the entire system of provincial and local governments, we have the option of requiring all procurement for Bank-financed contracts be handled by an independent Provincial/Regional Procurement Board to conduct prequaliflcation, tendering and bid evaluation in lieu of the normal tender committee. (Nothing in KEPRES 16 appears to forbid this as the Board could be designated by the implementing unit, as long as normal signature authorities were maintained.) Membership of the Board would be agreed between GOI and the Bank to include appropriate technical and community members.

4. Agree to finance realistic salary incentives/honoraria for staff of Bank project implementation units and appropriate operating budgets for the projects following the example of Bank health sector projects here (and many other projects worldwide), and encourage GOI and other donors to do the same. This would limit the budgetary impact of formally increasing compensation to only those civil servants working on development projects. (We could discuss broadening this principle with MenPAN.) However, the Bank could/should insist this be coupled with an announced and serious policy of zero tolerance for diversion of contract funds and serious penalties for any offenders.

5. Current unit prices/billing rates for essentially all goods, works and services procured by GOI include varying degrees of mark-up for diversion, as nearly all such prices are established from "standard unit prices" (as for MPW averaging recent contracts) or other measures of "current market prices". Efforts are underway (by Chitta B. and Frida) to analyse the pricing differential bet-Aleen public and private contracts for similiar works (Chitta), and between official versus community-based contracting (Frida). The preliminary results of these efforts seem to confirm mark-ups which average 15-40%, but showing quite a range of variation. International unit rates in sectors such as power and telecoms tend to limit this mark-up in the truly international ICB procurements. The Bank and GOI could thus establish a baseline or "benchmark" set of unit prices and billing rates for use in Bank projects and require clear justification of any variance.

6. Tighter supervision of physical implementation by both GOI and the Bank could reduce the instances of padded bills of quantity (BoQ) in contracts, substitution of inferior quality materials or equipment, improved quality of physical outputs and "results on the ground" of Bank projects. Of course, the budget and staffing implications of such increased supervision would have to be assessed and apportioned between the Bank and GOI, with perhaps the most convenient, but also the most expensive, solution being the hirng of consultants mandated to perform the increased supervision.

7. The use of "empowered engineers/consultants" as contract managers is an option already in use by PLN and other project agencies (and widely used in other countries), and which has been agreed in principle with GOI at our most recent CPPR discussions. Several major implementing agencies, including NTW, seem to regard the empowering of "project engineers" (usually foriegners) as a retrograde step to earlier operational methods used by the Bank, but discontinued in most sectors more than IO years ago due to (supposedly) growing in-house capacities in implementing units. Having such empowered consultants could be undertaken in conjunction with or separately from the independent procurement board noted in para. 3 above, but if both are done it has the effect of taking control of the project (except contract signature) away from the GOI implementing unit, and would certainly raise serious objections.

8. Mechanisms to increase public information and facilitate public involvement are being tried in several Bank projects, perhaps most notably in the VIP program where public information boards displaying project location, design and costs are posted in each project community, together with telephone number and other instructions for submitting comments, questions or complaints. Many RSI staff commenting on the issue have suggested increased transparency and encouragement of public monitoring/comment as an important mechanism we could use to better assure contractor performance and results. Project or RSI "hotlines" or comment/complaint mailboxes were also suggested to assure that the public or project staff could provide information while maintaining anonymity.

9. From the perspective of the Bank's fiduciary responsibilities, perhaps the most blatant and serious issue for immediate attention is improvement in the quality and accuracy of project financial audits now conducted for most projects by BPKP.

Most GOI project officers report visits by BPKP staff result in demands for payments in return for a "clean" (i.e. unqualifi6d) audit of their accounts. In summary, the audit results on which the Bank relies for satisfying our Judiciary responsibilities are for sale! There are really only two basic options: attempt to fix the problems at BPYP to produce the accurate, independent audits required by our loan agreements, or find other (commercial) auditors who can do the job. We must decide if we believe BPKP is "fixable" and if so quickly proceed with a loan (along the lines of the recent BPK project, but much stronger) to address the problems and produce reliable audit reports. Otherwise, we must convince GOI to retain commercial auditors, which they have consistently refused for more than 20 years (it may require a serious threat to suspend lending, if we mean it). Expansion of our audit coverage to include contractors books is also an option posed by some staff members and the HQ working group on corruption; but, the obvious question quickly becomes: who would pay for such audits and to whom would the auditors report?

10. Curtail Bank financing of "soft" expenditures such as TA, consultancies, training, travel and other project cost which are easv to falsify and difficult to audit. While many Bank staff correctly assert that much of the long-term impact of our projects comes from the intangible or "soft" activities which focus on capacity-building, transfer of knowledge and overcoming skills shortfalls, as well as inadequate routine budget allocations, it is also undeniable that these activities have suffered from some of the most serious cases of diversions and fraud encountered by our projects. Tightening supervision, better Terms of Reference, improved documentation and payment based on performance/outcome have all been suggested as partial remedies applicable to some Bank projects and these have been generally discussed in recent CPPR meetings. However, the problem is significant enough to deserve a place on the agenda for policy discussions with GOI.

11. Continued improvement in GOI-Bank procedures for land aquisition and resettlement, focusing both on assuring adequate budgets and actual payments to the affected persons. As noted in the problem statement, even when adequate funds are budgeted, "leakage" in the process of land aquisition and resettlement compensation remains a serious issue in many cases. Establishing a special GOI commission for land issues (along the lines of the human rights commission) is an option which could be explored, but no one on the GOI side has even hinted. that it may be acceptable.

12. Finally, and perhaps most basically, there is a clear feeling from the staff that such issues have not received Bank management attention until recently and some uncertainty as to feasibility of pursuing this agenda with GOI, especially now in the run-up to the Presidential election in March. However, there is broad concensus among the staff that "the problem starts at the top" and there is a sincere willingness (even eagerness by some) to support Bank efforts to escalate dialogue on these issues to the highest possible levels in GOI in our attempt to produce a meaningful program of action.


1 Asian Development Bank, Anti-Corruption Policy: Description and Answers to Frequently Asked Questions, Manilla, Philippines, 1999, p.5.

2 www.oecd.org/daf/nocorruption/faq.htm

3 According to a French secret service report, the official export credit agency of France paid around $2 billion in bribes to foreign purchasers of 'defence equipment' in 1994. See: Fiddler, S., "Defence contracts 'pervaded by graft'", Financial Times, 7 July 1999.

4 World Bank, Helping Countries Combat Corruption: Progress at the World Bank since 1997, World Bank, Washington DC, 2000, p.1.

5 World Bank, Helping Countries Combat Corruption: Progress at the World Bank since 1997, World Bank, Washington DC, 2000, p.1

6 Asian Development Bank, Anti-Corruption Policy: Description and Answers to Frequently Asked Questions, Manilla, Philippines, 1999, p.5. See also: Mauro, P., "Corruption and Growth", Quarterly Journal of Economics, 109: 681-712, 1995; Mauro, P., "The Effects of Corruption on Growth, Investment and Government Expenditure: A Cross-Country Analysis" in Kimberly Elliott (ed)., Corruption in the World Economy, Washington DC, Institute for International Economics, 1997. See: Susan Rose-Akerman, "Corruption and Good Governance", Paper presented at "Democracy and Development: The Role of International Organisations", An International Conference co-sponsored by UNDP and Yale University, Yale University, New Haven, 1997.

7 Asian Development Bank, Anti-Corruption Policy: Description and Answers to Frequently Asked Questions, Manilla, Philippines, 1999, p.1.

8 Atkinson, M. and Atkinson, D., "The Bung Bang", The Guardian, 13 December 1997, p.26.

9 "'20pc' of World Bank loans to Indonesia stolen", The Guardian, 21 August 1998

10 Asian Development Bank , Anti-Corruption Policy: Description and Answers to Frequently Asked Questions, Manilla, Philippines, 1999, p.5.

11 See also: Frisch, D., "The Effects of Corruption on Development", The Courier ACP-EU, No.158, July-August 1996, pp.68-70.

12 Asian Development Bank , Anti-Corruption Policy: Description and Answers to Frequently Asked Questions, Manilla, Philippines, 1999, p.5.

13 Asian Development Bank, Anti-Corruption Policy: Description and Answers to Frequently Asked Questions, Manilla, Philippines, 1999, p.5.

14 Asian Development Bank , Anti-Corruption Policy: Description and Answers to Frequently Asked Questions, Manilla, Philippines, 1999, p.5.

15 House of Commons, Hansard, Column 374, 25 February 1998.

16 Asian Development Bank , Anti-Corruption Policy: Description and Answers to Frequently Asked Questions, Manilla, Philippines, 1999, p.5.

17 Tucker, T., Personal Communication, 25th September 2000. NGOs in Bangladesh have raised major questions about the project, which resulted in severe social and environmental impacts.

18 Department for International Development, Departmental Report 2000 - The Government's Expenditure Plans 2000-2001 and 2001-2002 (Annex 5), London, April 2000. Just under half as much money is channeled through multilateral agencies as through bilateral programmes.

19 The Bank is governed through a 24-member Executive Board, on which the UK is represented, its voting share (4.3 per cent) being allocated on the basis of its contributions. Responsibility for UK policy with regard to the Bank rests with the Secretary of State for International Development. All projects have to be approved by the Board. The UK public has a right to expect that the UK Executive Director takes every care to ensure that projects are not approved unless measures are in place to ensure that UK taxpayers money channeled through the Bank is used for the purposes it was intended. For details of UK share, see: US General Accounting Office, World Bank: Management Controls Stronger, but Challenges in Fighting Corruption Remain, GAO/NSIAD-00-73, Washington DC, April 2000, p.21.

20 Rich, B., The Smile on a Child's Face: From the Culture of Loan Approval to the Culture of Development Effectiveness? The World Bank Under James Wolfensohn, Environmental Defense, Washington D.C., 1999.

21 Rich, B., The Smile on a Child's Face: From the Culture of Loan Approval to the Culture of Development Effectiveness? The World Bank Under James Wolfensohn, Environmental Defense, Washington D.C., 1999.

22 Rich, B., The Smile on a Child's Face: From the Culture of Loan Approval to the Culture of Development Effectiveness? The World Bank Under James Wolfensohn, Environmental Defense, Washington D.C., 1999: World Bank, Confidential Internal Document, Summary of RSI Staff Views regarding the problem of 'Leakage' from World Bank Projects Budget, Jakarta, August 1997.

23 In response to Winter's charges, the Bank's Vice-President for East Asia, Jean Michel Severeno, stated: "This [systematic corruption in World bank lending to Indonesia] is demonstrably untrue. We know exactly where our money is going." Severino also dismissed the Dice memorandum as "one person's view based on informal interviews." He also falsely argued that a follow up study by Jane Loos had failed to confirm Dice's findings - when in fact it had (see main text). See: Rich, B., The Smile on a Child's Face: From the Culture of Loan Approval to the Culture of Development Effectiveness? The World Bank Under James Wolfensohn, Environmental Defense, Washington D.C., 1999.

24 Estimated on basis on UK share of contributions (4.3%) to the World Bank's annual budget.

25 Quoted in Rich, B., The Smile on a Child's Face: From the Culture of Loan Approval to the Culture of Development Effectiveness? The World Bank Under James Wolfensohn, Environmental Defense, Washington D.C., 1999.

26 Geary, K., Grainger, M., Lang, C. and Hildyard, N., Dams Incorporated: The Record of Twelve European Dam Building Companies, Swedish Society for Nature Conservation, Stockholm, February 2000.

27 McCully, P., Silenced Rivers: The Ecology and Politics of Large Dams, Zed Books, London and New York, 1996.

28 Brown, P., "Forest Corruption Report Covered Up: Governments, big business, World bank and IMF named in investigation", The Guardian, 29 May 2000. See also: "Corruption in the Forestry Sector", NGO Resolution to IUCN-World Conservation Congress, Amman, Jordan, 2000.

29 US General Accounting Office, World Bank: Management Controls Stronger, but Challenges in Fighting Corruption Remain, GAO/NSIAD-00-73, Washington DC, April 2000, p.21. See also: The World Bank, Helping Countries Combat Corruption: Progress at the World Bank Since 1997, Washington DC, June 2000, p.2.

30 US General Accounting Office, World Bank: Management Controls Stronger, but Challenges in Fighting Corruption Remain, GAO/NSIAD-00-73, Washington DC, April 2000, p.36

31 The World Bank, Helping Countries Combat Corruption: Progress at the World Bank Since 1997, Washington DC, June 2000, p.1.

32 US General Accounting Office, World Bank: Management Controls Stronger, but Challenges in Fighting Corruption Remain, Report to Congressional Committees, GAO/NSIAD-00-73, Washington DC, April 2000.

33 US General Accounting Office, World Bank: Management Controls Stronger, but Challenges in Fighting Corruption Remain, Report to Congressional Committees, GAO/NSIAD-00-73, Washington DC, April 2000, p.15.

34 US General Accounting Office, World Bank: Management Controls Stronger, but Challenges in Fighting Corruption Remain, Report to Congressional Committees, GAO/NSIAD-00-73, Washington DC, April 2000, p.15

35 US General Accounting Office, World Bank: Management Controls Stronger, but Challenges in Fighting Corruption Remain, Report to Congressional Committees, GAO/NSIAD-00-73, Washington DC, April 2000, p.19.

36 US General Accounting Office, World Bank: Management Controls Stronger, but Challenges in Fighting Corruption Remain, Report to Congressional Committees, GAO/NSIAD-00-73, Washington DC, April 2000, p.20.

37 US General Accounting Office, World Bank: Management Controls Stronger, but Challenges in Fighting Corruption Remain, Report to Congressional Committees, GAO/NSIAD-00-73, Washington DC, April 2000, p.15.

38 US General Accounting Office, World Bank: Management Controls Stronger, but Challenges in Fighting Corruption Remain, Report to Congressional Committees, GAO/NSIAD-00-73, Washington DC, April 2000, p.15.

39 US General Accounting Office, World Bank: Management Controls Stronger, but Challenges in Fighting Corruption Remain, Report to Congressional Committees, GAO/NSIAD-00-73, Washington DC, April 2000, p.5.

40 Rich, B., The Smile on a Child's Face: From the Culture of Loan Approval to the Culture of Development Effectiveness? The World Bank Under James Wolfensohn, Environmental Defense, Washington D.C., 1999, p.17.

41 In 1993, for example, the Bank's Financial Reporting and Auditing Task Force reported that "less than 40 per cent of audited financial information is received by its due date, making it inconsequential for project management" and that "Financial statements received by the World bank frequently are not reviewed by Bank staff or are reviewed by staff without the necessary skills to identify significant problems and initiate appropriate action." See: Rich, B., The Smile on a Child's Face: From the Culture of Loan Approval to the Culture of Development Effectiveness? The World Bank Under James Wolfensohn, Environmental Defense, Washington D.C., 1999.

42 US General Accounting Office, World Bank: Management Controls Stronger, but Challenges in Fighting Corruption Remain, Report to Congressional Committees, GAO/NSIAD-00-73, Washington DC, April 2000, p.10. See also: World Bank , The World Bank Procurement Function - Adjusting to Emerging Needs, April 1998; World Bank, Loan Administration Change Initiative - Implementation Strategy Paper, Washington D.C., 29 June 1998.

43 US General Accounting Office, World Bank: Management Controls Stronger, but Challenges in Fighting Corruption Remain, Report to Congressional Committees, GAO/NSIAD-00-73, Washington DC, April 2000, p.14.

44 US General Accounting Office, World Bank: Management Controls Stronger, but Challenges in Fighting Corruption Remain, Report to Congressional Committees, GAO/NSIAD-00-73, Washington DC, April 2000, p.11.

45 US General Accounting Office, World Bank: Management Controls Stronger, but Challenges in Fighting Corruption Remain, Report to Congressional Committees, GAO/NSIAD-00-73, Washington DC, April 2000, p.11.

46 US General Accounting Office, World Bank: Management Controls Stronger, but Challenges in Fighting Corruption Remain, Report to Congressional Committees, GAO/NSIAD-00-73, Washington DC, April 2000, p.12.

47 US General Accounting Office, World Bank: Management Controls Stronger, but Challenges in Fighting Corruption Remain, Report to Congressional Committees, GAO/NSIAD-00-73, Washington DC, April 2000, p.12.

48 US General Accounting Office, World Bank: Management Controls Stronger, but Challenges in Fighting Corruption Remain, Report to Congressional Committees, GAO/NSIAD-00-73, Washington DC, April 2000, p.22.

49 US General Accounting Office, World Bank: Management Controls Stronger, but Challenges in Fighting Corruption Remain, Report to Congressional Committees, GAO/NSIAD-00-73, Washington DC, April 2000, p.28.

50 US General Accounting Office, World Bank: Management Controls Stronger, but Challenges in Fighting Corruption Remain, Report to Congressional Committees, GAO/NSIAD-00-73, Washington DC, April 2000, p.29

51 See: Hawley, S., "Exporting Corruption: Privatisation, Multinationals and Bribery", Corner House Briefing 19, The Corner House, Sturminster Newton, June 2000. P.17.

52 Wesberry, J., "International Finance Institutions Face the Corruption Eruption", Northwestern Journal of International Law and Business, 1998. See also, US General Accounting Office, World Bank: Management Controls Stronger, but Challenges in Fighting Corruption Remain, Report to Congressional Committees, GAO/NSIAD-00-73, Washington DC, April 2000, p.11.

53 Hawley, S., "Exporting Corruption: Privatisation, Multinationals and Bribery", Corner House Briefing No.19, The Corner House, Sturminster Newton, June 2000, p.12.

54 Financial Times, 7 January 2000.

55 Tucker, T., Personal Communication, September 2000.

56 Tucker, T., Personal Communication, September 2000.

57 World Bank, Letter to B. Pekeche, Principle Secretary at the Ministry of Natural Resources, 2 December 1994.

58 World Bank, Letter to B. Pekeche, Principle Secretary at the Ministry of Natural Resources, 2 December 1994. In the letter, Praful Patel of the Bank's Southern Africa Department, gripes: "While the undertaking of a management audit may be normal practice, the suspending of key management staff in order to conduct such an audit is most unusual. In our view, the absence of key members of senior staff from the project during this critical time could seriously jeopardize the progress of the project".

59 Tricarico, A., Dams on Trial: The World Bank and the "Cancer of Corruption - Donor Governments, Financial Institutions and TNC's Responsibilities in the Lesotho Case, Reform the World Bank Campaign, Rome, 2000, p.14. In a letter to the International Rivers Network, the Bank has stated that it only knew of the bribery in July 1999 (or a few months earlier). However, documents leaked in Switzerland reveal that Lesotho government requested the Swiss Supreme Court's assistance in investigating the bribery allegations in August 1997.

60 The evidence suggests that the Bank could have delayed building the dam for well over a decade if water management practices had been put in place. Antonio Tricarico notes: "High level officials admitted in early 1998 that phase 1B could easily be delayed for seven years if water demand managed had been implemented, and up to 11 years or more if new demand side strategies had successfully been put in place." See: Tricarico, A., Dams on Trial: The World Bank and the "Cancer of Corruption - Donor Governments, Financial Institutions and TNC's Responsibilities in the Lesotho Case, Reform the World Bank Campaign, Rome, 2000, p.14.

61 Tricarico, A., Dams on Trial: The World Bank and the "Cancer of Corruption - Donor Governments, Financial Institutions and TNC's Responsibilities in the Lesotho Case, Reform the World Bank Campaign, Rome, 2000, p.11.

62 Andrew Macoun, the Task Team Leader, Lesotho Highland Water states in a letter of 17 August 2000: "All information and records in the Bank's possession have been made available to the legal consultants, and any suggestion to the contrary is completely false."

63 Minutes of meeting between Wolfensohn and NGOs, 22 September 2000.

64 A confidential 1991 World Bank project document exposes the Bank's claim to be a passive bystander in the project as baseless. The document states; "In the early stages of project preparation, the Government of Lesotho explicitly requested that the Bank be the lead agency in the raising of the massive amounts of funds required for implementing the project and in helping guide the complicated and sensitive negotiations between Lesotho and the Republic of South Africa. That the proposed project has reached its current stage is clear evidence of the Bank having successfully fulfilled this role to date."

65 "IPP crisis - Pakistan risks financial collapse over private power policy", Power Economist, 30 June 1998, p.13.

66 "Expropriation by 2 countries is alleged - Pakistan, Indonesia criticised", Business Insurance, 2 November 1998.

67 Dunne, N. and Fiddler, S., "World Bank helped Sharif in corruption probe", Financial Times, 12 November 1999, p.12.

68 "Pakistani court blocks Hubco remittance", Reuters, 11 May 1998.

69 "IMF deal brings relief for Pakistan IPPs", Power Economist, 31 December 1998, p.15.

70 Wiehen, M. H., Transparency and Corruption Prevention in Building Large Dams, Paper for the World Commission on Dams, Cape Town, 26 December 1999. P.17

71 Wiehen, M. H., Transparency and Corruption Prevention in Building Large Dams, Paper for the World Commission on Dams, Cape Town, 26 December 1999. p.18

72 World Bank, Effective Implementation: Key to Development Impact, Portfolio Management Task Force, 1992, p.iii.

73 Rich, B., The Smile on a Child's Face: From the Culture of Loan Approval to the Culture of Development Effectiveness? The World Bank Under James Wolfensohn, Environmental Defense, Washington DC, 1999, pp.6-7. See also: World Bank Memorandum, Human Resources Policy Reform, 6 March 1998 (internal document).

74 See, for example: World Bank Quality Assurance Group, Portfolio Investment Prgram: Reviews of Sector Portfolios and Lending Instruments - A synthesis, 22 April 1997 (draft internal report), p.20; World bank, Operations Evaluation Department, Effectiveness of Environmental Assessments and National Environmental Action Plans - A process Study, Report No.15835, 29 June 1996, p.37; World bank, Operations Evaluation Department, Poverty Assessment: A progress Review, Report No. 15881, 7 August 1996; World bank, The World Bank Procurement Function - Adjusting to Emerging Needs, April 1998; World bank, Loan Administration Change Initiative - Implementation Strategy paper, 29 June 1998; World bank, Quality at Entry in Calendar Year 1998: A Quality Assurance Group Assessment, July 1999. Such reports highlight the undue optimism of project appraisals; the cynicism with which poverty assessments are regarded; the continuing weaknesses in assessing government commitment, local capacity and the more general risks involved in project implementation; and the insidious institutional effects of the pressure to lend.

75 The 1998 Loos Memorandum on Indonesia specifically identifies the pressure to lend as a major factor in corruption: "There is an inherent tension not only between volume/speed of commitments/ disbursements and the quality of our work, but also between these and potential leakages." See: Loos, J., "World Bank Office Memorandum to Mr. Jean-Michel Severino, Vice President, EAP", 19 October 1998.

76 World Bank Quality Assurance Group, "Portfolio Investment Program: Reviews of Sector Portfolios and Lending Instruments - A synthesis", 22 April 1997 (draft internal report), p.15.

77 World Bank Operations Evaluation Department, Indonesia Country Assistance Note, 4 February 1999, p.25.

78 World Bank Operations Evaluation Department, Indonesia Country Assistance Note, 4 February 1999, p.26.

79 World Bank Operations Evaluation Department, Indonesia Country Assistance Note, 4 February 1999, p.20.

80 Government of Karnataka, Report of the Comptroller and Auditor General of India for the Year Ended 31 March 1999, No.3, Karanataka, 1999, pp.51-63.

81 In all, 19 individuals and corporations are charged. The charge sheets relating to the UK companies are available from The Corner House.

82 See: ECGD Annual Reports and Trading Accounts for 1993/94, 1994/95. 1995/96 and 1996/97. The companies were: Balfour Beatty, Kier International, Stirling International, Kvaerner Boving and ABB Generation's UK subsidiary. Gibb, Balfour Beatty and their partners also received EU grants. See also: Jonathan Rugman, "British Backhanders in Lesotho", Channel 4 News, Special reports. Broadcast 14 June 2000.

83 Jonathan Rugman, "British Backhanders in Lesotho", Channel 4 News, Special reports. Broadcast 14 June 2000

84 The Lesotho Highlands Project Contractors.

85 The payments are detailed in the charge sheets against the consortium. See also: Jonathan Rugman, "British Backhanders in Lesotho", Channel 4 News, Special reports. Broadcast 14 June 2000

86 Funding for the project came from The World Bank; the European Investment Bank; the German, British and French bilateral aid agencies; the UK Commonswealth Development Corporation; commercial banks including Banque National de Paris, Dresdner and Hill Samuel; and a number of export credit agencies, including Germany's Hermes, France's COFACE and South Africa's SACCE.

87 Henke, D., "British Firms on Bribery Charges", The Guardian, 17 February 2000.

88 For further details, see: Geary, K., Grainger, M., Lang, C., Hildyard, N., Dams Incorporated - The Record of Twelve European Dam Building Companies, Swedish Society for Nature Conservation, Stockholm, February 2000.

89 ECGD Annual Report 1994/95

90 See paragraphs 42-43.

91 Ozanne, J. and Keeling, W., "Protest over Kenya Deal with UK firm", Financial Times, 9 January 1992.

92 Knight Piesold, Documents detailing dam projects obtained from the company, October 1999.

93 Control Risks, Corruption and Integrity: Best Business Practice in an Imperfect World, Control Risks, London 1996, cited in "Crime-Corruption: The World's Growth Industry", Inside Eye, October 1998.

94 Wheat, S., "Casting the First Stone", Developments, First Quarter, 1999, pp.15-17.

95 Frisch, D. "Export Credit Insurance and the Fight Against International Corruption", Transparency International Working paper, Brussels, 26 February 1999. www.transparency.de/documents.work-papers.dfrisch.html

96 Frisch, D. "Export Credit Insurance and the Fight Against International Corruption", Transparency International Working paper, Brussels, 26 February 1999. www.transparency.de/documents.work-papers.dfrisch.html

97 Caborn, R., Minister for Trade, Evidence to The International Development Committee, The Export Credits Guarantee Department, Development Issues and the Ilisu Dam: Minutes of Evidence and Appendix, House of Commons, Session 1999-2000, The Stationary Office, London, 1 February 2000, p.36.

98 Whiehan, M.H., Transparency and Corruption Prevention on Building Large Dams, Paper for the World Commission on Dams, Cape Town, 26 December 1999, p.19.

99 ECGD, Personal Communication, 9 March 2000.

100 Jackson, E., "Transnational Bribery: The Panama Connection", The Panama News, July 2000.

101 World Bank, Confidential Internal Memorandum, "Discussion Points Regarding Improved Transparency in Procurement Processes."

102 Caborn, R, Minister for Trade, Letter to Ilisu Dam Campaign,6 July 2000.

103 OECD, Report by the CIME: Implementation of the Convention on Bribery in International Business Transactions and the 1997 Revised Recommendation: Country Reports, OECD, Paris, 23 June 2000, p.428.

104 Details of the evidence against the companies is detailed in the charge sheets issued by the court in Lesotho, available from The Corner House.

105 OECD, Report by the CIME: Implementation of the Convention on Bribery in International Business Transactions and the 1997 Revised Recommendation: Country Reports, OECD, Paris, 23 June 2000, p.434. A company is criminally liable under the 1906 Act if a representative of the company committed a culpable act - but for criminal liability to be imposed on the company it is not necessary that the representative has been convicted of the offence in question.

106 Home Office, The Prevention of Corruption: Consolidation and Amendment of the Prevention of Corruption Acts 1889-1916 - A Government Statement, June 1997.

107 Caborn, R., Letter to Ilisu Dam Campaign, 6 July 2000

108 ECGD, Letter to World Development Movement, 7 August 2000

109 Hampton, M.P., "Where Currents Meet: The Offshore Interface Between Corruption, Offshore Finance Centres and Economic Development" in Harris-White B. and White, G., "Liberalisation and the New Corruption", IDS Bulletin, Vol.27 No.2 1996.

110 For a discussion, see for example: Sue Hawley, "Exporting Corruption", Corner House Briefing 19, June 2000: "Casting the First Stone", Developments, First Quarter, 1999, pp.15-17.

111 See: Sue Hawley, "Exporting Corruption", Corner House Briefing 19, June 2000.

112 "Letters", The Daily Telegraph, 26 June 2000.

113 For examples, see Hawley, S., "Exporting Corruption", Corner House Briefing 19, June 2000, p.22ff.

114 Quoted in Wiehen, M.H., Transparency and Corruption Prevention in Building Large Dams, Paper for the World Commission on Dams, Cape Town, 26 December 1999.

115 BICC plc, Annual Report and Accounts 1999; Balfour Beatty, Balfour Beatty 2000: A strong New PLC, London, 2000.

116 Balfour Beatty, Interim Report 2000, Balfour Beatty, London, 2000.

117 Bosshard, P. (in collaboration with Altemeier, I.), Publicly Guaranteed Corruption: Corrupt Power Plant Projects and the Responsibility of Switzerland, Berne Declaration, October 2000.

118 PowerGen plc, Annual Report 1999, p.6.

119 Corporate governance standards include the Combined Code appended to the listing rules of the London Stock Exchange (endorsed by Balfour Beatty) and the Code of Best Practice recommended by the Cadbury Committee.

120 Hawley, S., "Exporting Corruption", Corner House Briefing 19, June 2000, p.20.

121 Quoted in Sue Wheat, "Casting the First Stone", Developments, First Quarter, 1999, p.17.

122 See B. Harris-White and G. White, "Corruption, Liberalization and Democracy," IDS Bulletin, Vol. 27, No. 2, 1996.

123 Geary, K., Grainger, M., Lang, C., Hildyard, N., Dams Incorporated: The Record of Twelve European Dam Building Companies, Swedish Society for Nature Conservation, Stockholm, February 2000, p. 89. See also: Ozanne, J., "Mr. Biwott the businessman: A look at the former Kenyan minister's road to riches", Financial Times, 27 November 1991.

124 McCully, P., Silenced Rivers - The Ecology and Politics of Large Dams, Zed Books, London and New York, 1996, p.261.

125 Ozanne, J., "Mr. Biwott the businessman: A look at the former Kenyan minister's road to riches", Financial Times, 27 November 1991.

126 McCully, P., Silenced Rivers - The Ecology and Politics of Large Dams, Zed Books, London and New York, 1996, p.262.

127 Goldman, A and Wrong, M, "Survey - East African Community: Future looks brighter", Financial Times, 5 November 1996, p.4.

128 This section is drawn from: Geary, K., Grainger, M., Lang, C., Hildyard, N., Dams Incorporated: The Record of Twelve European Dam Building Companies, Swedish Society for Nature Conservation, Stockholm, February 2000

129 Information on Paiton derived from Bosshard, P. (in collaboration with Altemeier, I.), Publicly Guaranteed Corruption: Corrupt Power Plant Projects and the Responsibility of Switzerland, Berne Declaration, October 2000.

130 Bosshard, P. (in collaboration with Altemeier, I.), Publicly Guaranteed Corruption: Corrupt Power Plant Projects and the Responsibility of Switzerland, Berne Declaration, October 2000.

131 Bosshard, P. (in collaboration with Altemeier, I.), Publicly Guaranteed Corruption: Corrupt Power Plant Projects and the Responsibility of Switzerland, Berne Declaration, October 2000.

132 Channel 4 News

133 Tumisiime,J., "Madhvani in trouble with the World Bank", The Monitor, 12 August 2000.

134 Palast, G., "War on Corruption? Not quite, Minister", The Observer, 9 July 2000, Business, p.5